Attachment 3 - Construction Management Plan

of 17

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                        Westcon Site Management Pty Ltd



           • Dampening     of working areas, roadways and other hardstand areas when visual
             surveillance indicates excessive dust generation from stockpiles or mobile sources;
           • Enforcing a 30 kph speed limit on roadways;
           • Restricting mobile machinery movements to designated routes and standing areas;
           • Levelling of loads prior to truck exit from the site to avoid spillage;
           • Providing and maintaining truck wheel shaker facilities to prevent carriage of mud onto
             sealed public roads;
           • Covering all loads of fine materials;
           • Regular sweeping/washing of sealed access roads to remove mud and product spillages.


4.7       Waste Management

          Wastes generated by construction activities on the site must be managed in the following
          manner:

           • Sorting and storing paper and general wastes from office and construction activities in
             appropriate containers prior to disposal off site at designated landfill, transfer station or
             recycling depot;
           • Temporarily storing scrap metals in a designated holding area prior to collection by
             scrap metal merchant for recycling;
           • Temporarily storing concrete waste in a designated bin or area prior to collection by a
             contractor for recycling;
           • Removing silt from sediment traps and silt fences to a designated storage area for drying
             prior to being incorporated into revegetation works; and
           • Using waste water from sediment traps for dust control.


4.8       Noise Management

          The following management practices will be adopted at the construction site:

           • Designing the layout of the construction area to maximise the use of natural barriers,
            earthen bunds and vegetation;
           • Restricting hours of construction so that all activities including maintenance, refuelling
             and servicing of equipment will only be undertaken between the hours 7.00 am to 6.00
             pm Monday to Friday and 7.00 am to 2.00 pm on Saturday subject to compliance with
             noise provisions of the Environmental Protection Act or local council ordinances;
             Induction of new employees on the requirements of the Noise Management
             requirements of the CMP.
           • Subcontracted services are to be monitored to:
                o Operate and maintain modern, well maintained road worthy vehicles fitted with
                  high efficiency mufflers;
                o Avoid unnecessary revving of mobile or stationary motors;
                o Restrict vehicle speeds to less than 30 kilometres per hour on the site;
                o Maintain roadways in good condition;




Issue 2              July 1                                                             Page 12
Log in to download the original file

Attachment 3 - Construction Management Plan.pdf · 259 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.