• Dampening of working areas, roadways and other hardstand areas when visual
surveillance indicates excessive dust generation from stockpiles or mobile sources;
• Enforcing a 30 kph speed limit on roadways;
• Restricting mobile machinery movements to designated routes and standing areas;
• Levelling of loads prior to truck exit from the site to avoid spillage;
• Providing and maintaining truck wheel shaker facilities to prevent carriage of mud onto
sealed public roads;
• Covering all loads of fine materials;
• Regular sweeping/washing of sealed access roads to remove mud and product spillages.
4.7 Waste Management
Wastes generated by construction activities on the site must be managed in the following
manner:
• Sorting and storing paper and general wastes from office and construction activities in
appropriate containers prior to disposal off site at designated landfill, transfer station or
recycling depot;
• Temporarily storing scrap metals in a designated holding area prior to collection by
scrap metal merchant for recycling;
• Temporarily storing concrete waste in a designated bin or area prior to collection by a
contractor for recycling;
• Removing silt from sediment traps and silt fences to a designated storage area for drying
prior to being incorporated into revegetation works; and
• Using waste water from sediment traps for dust control.
4.8 Noise Management
The following management practices will be adopted at the construction site:
• Designing the layout of the construction area to maximise the use of natural barriers,
earthen bunds and vegetation;
• Restricting hours of construction so that all activities including maintenance, refuelling
and servicing of equipment will only be undertaken between the hours 7.00 am to 6.00
pm Monday to Friday and 7.00 am to 2.00 pm on Saturday subject to compliance with
noise provisions of the Environmental Protection Act or local council ordinances;
Induction of new employees on the requirements of the Noise Management
requirements of the CMP.
• Subcontracted services are to be monitored to:
o Operate and maintain modern, well maintained road worthy vehicles fitted with
high efficiency mufflers;
o Avoid unnecessary revving of mobile or stationary motors;
o Restrict vehicle speeds to less than 30 kilometres per hour on the site;
o Maintain roadways in good condition;
Issue 2 July 1 Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.