SUPERSEDED - Decision Notice - 010.2007.00002446.001 [As Published] · 132007.2446
2007/2446
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
18. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
Relevant Period
19. The Development Permit for a material change of use of premises lapses if the use has not
happened by 17 August 2013, unless an application to extend the relevant period is
approved by Council.
Frontage Works
20. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants
& Guidelines. Grass shall be couch, free of weeds.
21. The applicant shall be responsible for providing an edge-of-road yellow line marking
between the proposed Entry and Exit driveways from the site to indicate “No Parking” area.
The line marking shall be provided in accordance with Manual of Uniform Traffic Control
Devices (MUTCD) Part 3 and shall be indicated on the plans submitted for Development
Permit for Operational Works.
22. All paths, ramps, driveways and parking areas shall be designed and constructed to ensure
pedestrian safety using non-slip materials, to produce an evenly graded surface finish, and
to be in accordance with the Disability Discrimination Act 1992 and Australian Standard
1428.1 Design for Access & Mobility.
23. All redundant vehicular crossings to the site shall be removed and replaced by kerb &
channel, footpath paving and landscaping such as trees and grasses in accordance with
Council’s Standard specifications prior to commencement of the use permitted by this
permit.
24. The applicant shall replace the existing length of the kerb line between the proposed
driveways (Entry and Exit).
Roof Water & Stormwater Drainage
25. Roof runoff from any new building shall be directed to a rainwater storage system or tank
that is installed to ensure water from the rainwater storage system or tank is used for
external uses (such as watering gardens, irrigation, ornamental ponds, water features,
topping-up swimming pools, outdoor cleaning, etc) and for internal (ground floor) use in
washing machine cold taps and toilet cisterns. All rainwater tanks are to be designed and
installed in accordance with the Queensland Development Code (QDC) current at the time of
building approval, and shall be part of the plumbing application for approval. The location
and capacity of the tanks shall be clearly shown on the plans submitted for Building Works
and Operational Works approval and any overflow shall be directed to the road frontage/the
stormwater drainage system/etc located in Pacific Avenue.
26. All stormwater drainage (including roof water overflow from the rainwater storage system)
shall be collected and discharged so there is no net increase in stormwater runoff from the
site. Stormwater drainage permitted to drain from the site shall be discharged into Council’s
existing drainage structure (drainage pit at the frontage of the site in Pacific Avenue). Plans
of the drainage design shall be prepared by a Registered Professional Civil Engineer and
submitted to Council prior to obtaining a Development Permit for Operational Works.
Page 4 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Decision Notice - 010.2007.00002446.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 90 KB (small file)
- File type
No other editions are linked here.