including milling. However, as timber harvesting or milling is not required as part of the
development, it is recommended that the condition not require logs to be stockpiled for
transportation and/or milling. Instead, the condition should provide flexibility for suitable timber to
be retained or removed for beneficial reuse.
An additional advisory note is recommended.
Recommendation
It is recommended existing condition 25 be amended to read as follows:
26. After under scrubbing of each area is complete, non-habitat trees (i.e. trees other than those
identified as habitat trees) will may be cleared and stockpiled for mulching. Suitable felled
timber may be retained or removed from the site for beneficial reuse, with remaining
felled vegetation stockpiled for mulching. Clearing of non-habitat trees will only occur
where their removal will not impact on identified habitat trees (e.g. canopies do not
interconnect with habitat trees).
3. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme. The
requested changes to the conditions do not raise any significant issues and are therefore
supported. The application is therefore recommended for approval.
The report is provided in accordance with Section 76 of the Planning Act 2016.
RECOMMENDATION
With regard to Application No. OPW26/0033, and the representations made, Council on 29
September 2026 decided to:
A. Agree to amend conditions 10, 17 and 25 to read as follows:
10. Submit a Construction Management Plan to Council prior to the pre-start meeting. The
Construction Management Plan must be prepared for phase one of works which relates to
Clearing Vegetation under Planning Scheme and must specifically address the following:
a. traffic management during the clearing of vegetation including:
i. a Traffic Management Plan in accordance with the Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to the commencement of the vegetation clearing;
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. Proposed fencing to the site during the construction phase of the development;
iv. Adequate parking arrangements for constriction workers, residents and
delivers; and
v. No queuing of trucks is permitted on residential streets;
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
controls;
c. Works programme identifying key components of the clearing works and their
respective durations;
d. Establishment of a communication protocol with the adjoining owners and local
residents affected by the clearing works, to advise of agreed clearing times, impacts
on access and services and other relevant issues;
Page 7 of 9
Document Set ID: 25207630
Version: 3, Version Date: 02/10/2026