                                             (c) the structure does not
                                                 exceed 7 metres in width;
                                                 and
                                             (d) each jetty is a maximum of
                                                 1.5 metre wide.

Fixed Floating Structures & Boat Ramps within Noosa Waters Estate waterways
PO22                                     No acceptable outcome provided         The applicant has not specifically   The Project is not within the
Fixed floating structures whether or                                            addressed the Waterways works        Noosa Waters Estate waterways
not attached to land (e.g. pontoons                                             code.                                therefore PO22 is not
and any associated walkways) and boat                                                                                applicable.
ramps are not located within the Noosa
Waters Estate.
Flooding and amenity functions - operational works within Noosa Waters Estate waterways
PO23                                     AO23.1                                 The applicant has not specifically   The Project is not within the
The flood detention and amenity          For premises adjoining a waterway      addressed the Waterways works        Noosa Waters Estate waterways
functions of the area adjacent to the    within the Noosa Water estate, no      code.                                therefore PO23 is not
revetment wall within Noosa Waters       building work, filling or excavation                                        applicable.
Estate are retained and enhanced by      works within 4.5 metres of the
ensuring—                                centre line of the top of the concrete
    (a) works do not protrude through revetment wall.
         a batter line of 1:4.5 measured
         from the centre line of the     AO23.2
         revetment wall;                 A minimum of 25% of the area
    (b) there is no additional load      within 4.5 metres of the revetment
         placed on the revetment wall;   wall is planted with shrubs and small
    (c) works do not pose a risk to the trees with a mature height of 3
         membrane adjoining the          metres or less.
         revetment wall;
    (d) amenity of the waterway and      AO23.3
         surrounding land uses is not    The ground surface within the first
         adversely affected by           metre of the revetment wall—
                                             (a) is grass or ground cover; and
Log in to download the original file

2022-05-16 GC Agenda - Item 7 - Attachment 1 - Report from Marine Approval Specialists(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.