Performance outcome Acceptable outcome Applicant response Assessment
the land on which it is
located;
(c) if a relevant planning scheme
standard is more stringent
than the standard mentioned
in paragraph (a) or (b)—the
relevant planning scheme
standard, to the extent it is
more stringent than the
standard mentioned in
paragraph (a) or (b).
13.2 Prescribed tidal works that are a (s 5(2) outcome) Not applicable. The Project is not a boat ramp or
boat ramp or slipway for a The design and construction of the Not a boat ramp or slipway therefore PO13.2 is not
private purpose are designed and boat ramp or slipway is consistent slipway. Not a private applicable.
constructed in a way to ensure with the following standards— purpose.
the safe movement of vehicles or (a) subject to paragraph (d), the
persons over the boat ramp or upper surface of a boat ramp
slipway. or slipway has a width of—
(i) for a boat ramp or
slipway with vehicle
access—no less than
3.6m; or
(ii) for a boat ramp or
slipway without vehicle
access—no less than
3.0m;
(b) subject to paragraph (d), the
whole upper surface of a boat
ramp or slipway is treated to
prevent it from becoming
slippery by using any of the
following methods—
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.