2022-05-16 GC Agenda - Item 7 - Attachment 1 - Report from Marine Approval Specialists

of 80

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Performance outcome                     Acceptable outcome                    Applicant response   Assessment
                                        the waterfront boundary of
                                        the lot connected to the deck;
                                        (b) subject to paragraph (c), a
                                        prescribed deck is at least 3m
                                        inside of the side boundary or
                                        extended side boundary of
                                        the lot connected to the deck;
                                        (c) if a relevant planning scheme
                                        standard is more stringent
                                        than the standard mentioned
                                        in paragraph (a) or (b)—the
                                        relevant planning scheme
                                        standard, to the extent it is
                                        more stringent than the
                                        standard mentioned in
                                        paragraph (a) or (b).
Design, construction and safety—boat ramps and slipways for private purpose
13.1 Prescribed tidal works that are a  (s 5(2) outcome)                      Not applicable.      The Project is not a boat ramp or
boat ramp or slipway for a              The design and construction of the    Not a boat ramp or   slipway therefore PO13.1 is not
private purpose are designed and        boat ramp or slipway is consistent    slipway.             applicable.
constructed in a way to ensure          with the following standards—
they are structurally sound while       (a) subject to paragraph (c), the
also ensuring the safe movement         walls at the edge of the boat
of vehicles or persons between          ramp or slipway penetrate
the boat ramp or slipway and the        into the earth at least 600mm
surface of the land on which the        below the surface of the land
boat ramp or slipway is located.        on which the boat ramp or
                                        slipway is located;
                                        (b) subject to paragraph (c), the
                                        surface of the boat ramp or
                                        slipway is no more than
                                        200mm above the surface of
Log in to download the original file

2022-05-16 GC Agenda - Item 7 - Attachment 1 - Report from Marine Approval Specialists(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.