Performance outcome Acceptable outcome Applicant response Assessment
than the standard mentioned
in paragraph (a), (b) or
(c)—the relevant planning
scheme standard, to the
extent it is more stringent
than the standard mentioned
in paragraph (a), (b) or (c).
Design, construction and safety—bridges
14.1 Prescribed tidal works that are a The design and construction of the Not applicable The Project is not a bridge therefore
bridge do not adversely affect bridge is consistent with the Not a bridge PO14.1 is not applicable.
existing public use of tidal following standards—
water, including, for example, (a) subject to paragraph (b), the
use of the tidal water for clearance levels under a
canoeing, swimming or other bridge are high enough to
recreational activities. allow continued public use of
tidal water over which it is
constructed;
(b) if a relevant planning scheme
standard is more stringent
than the standard mentioned
in paragraph (a)—the
relevant planning scheme
standard, to the extent it is
more stringent than the
standard mentioned in
paragraph (a).
14.2 Prescribed tidal works that are a The design and construction of the Not applicable The Project is not a bridge therefore
bridge do not adversely affect bridge is consistent with the Not a bridge. PO14.1 is not applicable.
the flow of tidal water under the following standards—
bridge. (a) subject to paragraph (b)—
(i) if a bridge can be
adequately supported
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.