RESPONSE
Please refer to the Engineering Plan prepared by Robert Bird Group (RPEQ 8261) in Attachment 2. This plan
details the extent of the proposed driveway expansion and includes a turn path analysis for the revised design
depicted in Attachment 1.
Please be advised that a longitudinal section plan and details regarding the levels and grades of the driveway
will be submitted to Council upon the resolution of all other matters contained within this correspondence.
ITEM 7
A site inspection indicates that the construction of the proposed driveway will potentially
impact a mature and well established tree within the road reserve. Council are concerned
that the location of the proposed driveway will create a potential conflict between the low-
lying canopy of the existing tree and vehicles using the driveway.
Information Required
Provide additional detail (species, size, height, etc) demonstrating if the existing tree is to be removed
or how the health of the existing tree will be managed during the proposed works and in the longer
term. If the existing tree is to remain, demonstrate that a B99 vehicle will not collide with the low-lying
canopy of the existing tree.
RESPONSE
Please refer to the revised Proposal Plan prepared by Essess Building Design in Attachment 1. The revised
driveway design shown in Attachment 1 ensures the retention of the existing street tree in the verge.
The applicant has also opted to provide a letter to Council detailing the context of the proposal and intention
for the development of the site. Please find this correspondence enclosed in Attachment 3.
This represents our complete response to the Further Advice notice issued by Council. We look forward to the
Decision Notice being issued by Council in accordance with the relevant provisions of the Planning Act 2016.
As always, please feel free to contact me direct should you require any additional information or clarification.
Yours faithfully,
ADAMS + SPARKES
TO WN P L AN N IN G
Cameron Adams
MANAGING DIRECTOR
ENC: Revised Proposal Plan prepared by Essess Building Design (Attachment 1)
Engineering Plan prepared by Robert Bird Group (RPEQ 8261 (Attachment 2)
Applicant correspondence to Council (Attachment 3)
Page 4 of 4
Our ref: 220325
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
ASTP-Resp-To-FA.pdfRelated documentApplication case desk ↗
About this file
- File size
- 484 KB (small file)
- File type
No other editions are linked here.