2010/627
General
20. The relevant period is four (4) years from the day this permit takes effect and ends on
13 September 2012, during which time all conditions must have been compiled with, and the
Plan of Survey lodged with Council for endorsement
21. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
22. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
23. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Water and Sewerage
24. Reticulated water must be provided to each lot in the development. This must include:
24.1 Ensuring that existing internal water pipes are wholly contained within the lot they will
serve.
24.2 A new 150mm diameter DICL watermain must be constructed from the existing 100mm
diameter AC watermain in David Low Way to the development, and for the full frontage
of the development site. The works must be completed prior to placing construction
materials or site offices adjacent to the water main alignment
24.3 An approved water meter for each lot in accordance with Unitywater Standard Drawings
SCW 350,355 and 360.
25. Proposed lot 3 is to be dedicated council open space and is not subject to development and
therefore water services will not be required.
26. Reticulated sewerage must be provided to each lot in the development. This must include:
27. Ensuring existing sewer house drains are wholly contained within the Lot they will serve.
28. The existing 150mm sewer and manholes located within the development site is to be disused
and a new sewer is to be constructed following a standard alignment to the property boundary
and in accordance with the council planning scheme. These works are to be submitted with
the associated operational works application.
29. Proposed lot 3 is to be dedicated council open space and is not subject to development and
therefore sewer services will not be required.
30. Retaining walls running horizontally to sewer mains are to be 1.5m clear of the sewer.
Retaining walls crossing the sewer are to be free standing and self supporting for a minimum
of 1m both sides of the sewer main.
31. The level of the existing sewer access chamber must be adjusted to suit the proposed finished
surface levels. Work must be undertaken by Unitywater at the applicants cost.
32. A minimum clearance of 1.5 metres must be maintained between Unitywater sewers and
proposed building envelopes, buildings and other structures.
33. A 3.0 metre wide easement must be provided over all Unitywater sewers located in private
property. A 4.0 metre wide easement must be provided over Unitywater sewers greater than
3.0 metres deep (where approved by Unitywater). Easements must be located centrally over
the main.
34. Written approval to enter and construct must be obtained from the owners of properties
through which external sewers will traverse, and be submitted with lodgement of the
associated development application for Operational Works
Page 4 of 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SPA Decision Notice - 010.2010.00000627.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 383 KB (small file)
- File type
No other editions are linked here.