6. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
7. A minimum maintenance period of 12 months will apply to all municipal works and
thereafter until such time as the works are performing in accordance with the approved
design unless noted otherwise
Environmental Advisory Notes
8. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all
reasonable and practicable measures to prevent or minimise the harm. Environmental
harm includes environmental nuisance. In this regard persons and entities, involved in the
civil, earthworks, construction and landscaping phases of this development are to adhere
to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
9. Accepted best practice standards include:
a. the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2
or other superseding document subsequently adopted by Council;
b. Best Practice Erosion and Sediment Control, International Erosion Control Association
(2008).
10. As a general rule, a site is determined to have achieved effective short-term stabilisation
if at the time of the On-Maintenance inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as
in the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for the On-Maintenance inspection, the method of short-term
stabilisation has not achieved a level of stability that Council's Officers believe will have
a high probability of achieving long term stability, Council Officers may take the
following matters into consideration in determining whether the site is capable of
achieving medium to long-term stability:
• evidence that the site has been effectively stabilised in the short term;
• evidence that soil has been adequately ameliorated;
• evidence that seed of annual and perennial grass species has been applied at
an adequate rate; and
• that grass seed has germinated at a density that is likely to achieve an effective
grass cover.
Landscape Works
11. The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
Register where:
a. An inspection revealed that any constructed rehabilitation/landscape works do not
comply with the conditions of the Decision Notice, Approved Plans and or Approved
Documents
b. Certification is submitted to Council falsely stating that works comply with the approved
plans, documents and or conditions of the Decision Notice.
Page 11 of 13
Document Set ID: 22809336
Version: 4, Version Date: 13/02/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - OPW19 0203 03 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 185 KB (small file)
- File type
No other editions are linked here.