CURRENT CONDITION COMMENT / REQUIRED CHANGE TO CONDITION
These works must be completed prior to the sealing accommodate the 3-point turn manoeuvre of a Waste
of the Survey Plan for Stage 2. Collection Vehicle WCV); and
(c) Stage 3: (v) installation of street lighting where necessary.
(i) All roads - 6 metre wide kerb to kerb formationThese works must be completed prior to the sealing of
within a 20 metre wide road reserve; the Survey Plan for Stage 2.
(ii) cul-de-sac turnaround areas with a minimum 9 (c) Stage 3:
metre radius and a minimum 4 metre wide verge at (i) All roads - 6 metre wide kerb to kerb formation
any point on the turning circle; and within a 20 metre wide road reserve;
(iii) installation of street lighting where necessary.
(ii) cul-de-sac turnaround areas with a minimum 9
metre radius and a minimum 4 metre wide verge at
These works must be completed prior to the sealing any point on the turning circle; and
of the Survey Plan for Stage 3. (iii) installation of street lighting where necessary.
These works must be completed prior to the sealing of
the Survey Plan for Stage 3.
Access Easement
24. The access driveway within the access easement Condition 24 needs to be updated to reflect the
within Lot 52 as shown on the Approved Plans must revised layout and staging boundaries as follows:
be constructed. The works must be undertaken in
accordance with an Operational Works approval and 24. The access driveway within the access easement
must be: within Lot 40 52 as shown on the Approved Plans must
(a) Aligned generally along the centreline of the be constructed. The works must be undertaken in
existing track and varied where necessary to preserve accordance with an Operational Works approval and
existing significant vegetation; must be:
(b) Constructed with a 4 metre wide gravel formation, (a) Aligned generally along the centreline of the
and existing track and varied where necessary to preserve
(c) Include passing bays where sight lines are existing significant vegetation;
obstructed (b) Constructed with a 4 metre wide gravel formation,
These works must be completed prior to the sealing and
of the Survey Plan for Stage 4. (c) Include passing bays where sight lines are
obstructed
These works must be completed prior to the sealing of
the Survey Plan for Stage 3 Stage 4.
Pedestrian and Bicycle Facilities
25. The developer must construct a minimum 2.5m Condition 25 needs to be updated to reflect the
wide concrete path on a 4m wide formation along the revised layout as follows:
proposed fire trail to the north of Lots 14 and 16
boundaries. The works must be undertaken in 25. The developer must construct a minimum 2.5m
accordance with an Operational Works approval and wide concrete path on a 4m wide formation along the
must: proposed fire trail to the north of Lots 36 to 39 14 and
(a) Be of sufficient dimensions and structural integrity 16 boundaries. The works must be undertaken in
to cater for use by emergency vehicles, accordance with an Operational Works approval and
(b) Be designed and constructed to ensure must:
pedestrian safety using non-slip materials, to produce (a) Be of sufficient dimensions and structural integrity
an evenly graded surface finish and to be in to cater for use by emergency vehicles,
accordance with the Disability Discrimination Act (b) Be designed and constructed to ensure pedestrian
1992 and Australian Standard 1428.1 Design for safety using non-slip materials, to produce an evenly
Access & Mobility graded surface finish and to be in accordance with the
JFP Ref: M1775 Page 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.