13. Provide additional detail and indicate on the plans the proposed methods for
waste/refuse storage and collection. The detail must be in accordance with
The Noosa Plan 2020 (Waste Management Code and PSP9 Waste
Management) and include but not be limited to:
a. Dimensioned storage areas
b. Bin collection locations and any required hardstand
Waste from the three units is to be stored in 6 wheelie bins within the garage and are to be wheeled
out to Bottlebrush Ave in the new carparking splays. These areas will be used one morning a week
for residential rubbish and recycling collection. The body corporate is to coordinate the movement
of the bins and responsibilities within the CMS.
14. Provide additional detail on the design rain event for the drainage system
and demonstrate that the design rain event is in accordance with The Noosa
Plan 2020 (Use Code, Works Codes and PSP 6)
15. Provide comment that confirms that the proposed system has been designed
considering climate change (20% increase in rainfall intensities)
16. Provide additional comment on how the impacts of rain events that exceed
the capacity of the proposed underground system will be addressed
Recor have provided updated stormwater sections and calculations, with new stormwater
drainage along the boundaries to diverst upstream runoff and overflow around the outside
of the building and through landscaping and pathway areas to Bottlebrush Ave and
Berrima Row.
Page 8 of
10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
response to info 37 bottlebrush.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.