2212-32529 SRA Response with conditions
Attached to the e-mail MCU22/0203 and OPW22/0304 - SRA application correspondence - SARA referral agency response.
2212-32529 SRA
No. Conditions Condition timing
(b) Submit the hydrographic survey plan to [email protected] or
mailed to:
Department of Environment and Science
Permit and License Management
GPO Box 2454
Brisbane Qld 4001
The chief executive administering the Planning Act 2016 nominates the Director-General of Agriculture and
Fisheries to be the enforcement authority for the development to which this development approval relates
for the administration and enforcement of any matter relating to the following conditions:
11. Development authorised under this approval is limited as follows: At all times
Operational work for the permanent removal, destruction or damage of
marine plants for beach nourishment being limited to 244.2m2 of dead
marine wood and shown in Figure 2-1 of Dog Beach Sand Nourishment
project: Marine Plant Monitoring Plan prepared by BMT, reference
R.A10342.002.00.Marine Plant MP.docx
Operational work for the temporary removal, destruction or damage of
marine plans for beach nourishment being limited to 45.9 m2 of subtidal
detritus and shown in Figure 2-1 of Dog Beach Sand Nourishment
project: Marine Plant Monitoring Plan prepared by BMT, reference
R.A10342.002.00.Marine Plant MP.docx
12. The dredging and beach nourishment must be carried out generally in At all times
accordance with the following plans:
- General Arrangement prepared by BMT, reference A10342-02-
02; and
- Typical Sections and Volumes prepared by BMT reference
A10342-02-03.
13. The marine plant monitoring must be undertaken generally in Monitoring:
accordance with Dog Beach Sand Nourishment project: Marine Plant
Monitoring Plan prepared by BMT, reference R.A10342.002.00.Marine
Plant MP.docx A post construction
monitoring survey
Monitoring reports must be submitted to [email protected] in
within two months of
accordance with Table 2-1 of the Dog Beach Sand Nourishment project:
construction
Marine Plant Monitoring Plan.
completion;
Six months after the
post-construction
survey; and
Yearly for a period of
three years after
completion of the
works.
State Assessment and Referral Agency Page 6 of 13