16-001014-02A (Ultimate SCMMP)

Attached to the e-mail Operational Works Application OPW16/0203 - 4 of 4.

of 192

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (14.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Purpose: To ensure earthworks bulking out, trimming and profiling and the key levels of functional (hydraulic) structures
are in accordance with design drawings and specifications. The earthworks and structures dictate the movement of
stormwater through the bioretention system and are a critical element in the function of the system.
                                                                                           Action (if
Items                                     Checked              Satisfactory                                                 Initial
                                                                                           unsatisfactory)
As constructed survey completed and
attached to this form

Photos taken and attached to this form

Set-out of system is correct

Base levels are at correct elevation
(+50 mm)

Base at correct grading (0.5%)

Punch out holes in overflow pit are
correct size, correct level and above
invert level of outlet pipe (+25 mm)
Overflow pit is correct size and crest
and invert is at correct level (+25 mm)
Outlet pipe invert levels are correct
(upstream and downstream) (+25 mm)

Outlet pipe is free draining

Overflow weir (if required) is correct
length and at correct level (+25 mm)
Overflow weir (if required) is keyed
into bund
Bunds/embankments surrounding the
system are at correct levels or above

HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)




NB: As constructed survey and drawings and photos attached.


Signed by superintendent:
Print name:
Date:
AND
Signed by bioretention designer:
Print name:
Date:
FORM B — Under-drainage

Purpose: To ensure under-drainage is installed correctly before the bioretention media is installed.



                               CONSTRUCTION AND ESTABLISHMENT SIGN-OFF FORMS – BIORETENTION
                                                                                   SYSTEMS                                      4

                                                               © South East Queensland Healthy Waterways Partnership 2010
Log in to download the original file

16-001014-02A (Ultimate SCMMP).pdf · 14.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.