16-001014-02A (Ultimate SCMMP)
Attached to the e-mail Operational Works Application OPW16/0203 - 4 of 4.
The original of this document is very large (14.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Final constructed levels are
consistent with design levels
Under-drainage clean-outs
extended 50–150 mm above filter
media
Under-drainage pipes flushed to
remove initial ingress of material
HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.
Comments (attach and refer to additional pages if necessary)
NB: As constructed survey and drawings and photos attached.
Signed by superintendent:
Print name:
Date:
AND
Signed by bioretention designer:
Print name:
Date:
FORM E — Coarse Sediment Forebay
Purpose: To ensure the coarse sediment forebay is constructed correctly.
Action (if
Items Checked Satisfactory Initial
unsatisfactory)
Extent of coarse sediment forebay
correctly set out
Rocks to be used to line base of
forebay are correct size and shape
Base of constructed forebay is flat
and set at the correct level below
the surface of the filter media
CONSTRUCTION AND ESTABLISHMENT SIGN-OFF FORMS – BIORETENTION
SYSTEMS 8
© South East Queensland Healthy Waterways Partnership 2010
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.