16-001014-02A (Ultimate SCMMP)

Attached to the e-mail Operational Works Application OPW16/0203 - 4 of 4.

of 192

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (14.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

SAFETY IN DESIGN HAZARD REPORT


                                                      App?                                                                                                                          Action
                  Consideration                                           Hazard / Comment                               Controlling Action                      Action By
                                                                                                                                                                                  Status

 Existing site conditions:

 Contaminated materials including biological                    N/A
 hazards                                                
 Existing services including relocations                        Potential injury/death due to striking of   Appropriate warning notes provided on              Designer /        Complete on
                                                                existing services located along roads,      engineering plans. DBYD investigation              Contractor        plans/
                                                                external intersections                      undertaken and design has been
                                                                                                           undertaken to minimise risk due to existing
                                                                                                                                                                                 Ongoing for
                                                                                                                                                                                 construction
                                                                                                            services. Contractor to locate all services
                                                                                                            prior to ground disturbance/excavation.
 Existing site uses and users                                  No existing users

 Adjacent land uses and users                                   Risk of unauthorised entry and works        Contractor/Principal to provide adequate           Contractor/       Prior to
                                                                near public road.                           site controls including fencing if required to     Principal         Construction
                                                                                                           perimeter of the site to limit access and
                                                                                                            reduce risks associated with unauthorised
                                                                                                            entry
 Geotechnical conditions and likely method of                   Conventional, however deep                  All works to be undertaken in accordance           Contractor        During
 excavation                                                     excavations are likely and additional       with standards and WH&S requirements.                                Construction
                                                               control measures may be required by
                                                                contractor
 Ground water                                                   Likely to be encountered in low lying       To be managed by contractor and                    Contractor/       During
                                                               areas and gullies.                          superintendent during construction.                Superintend       Construction
                                                                                                                                                               ent
 Susceptibility to flooding including overland                  Overland flowpaths exist with the           Gullies and channels to be avoid during            Contractor        During
 flow paths and floodways                                      potential for significant flooding along    times of high rainfall                                               Construction
                                                                the main gullies
 Existing provision for access including traffic,               Hazards associated with existing road       Appropriate traffic management to be               Contractor        During
 residential, pedestrian, equestrian, etc.                     surrounding the site.                       implemented by the contractor throughout                             Construction
                                                                                                            the duration of the works
 Existing bus routes and bus stops                      
 Existing features of cultural, archaeological,                 None associated with Stage 1A
 heritage and / or environmental significance                  Central Wetland
 Design:


Document: QAF2024 Safety in Design Hazard Report – Generic
Revision 10 – 10/02/2015                                                                                                                                                         Page 2 of 12
File: H:\B14\150-199\B14158.W\01 Final Layout Op Works\Checklists\B14158.W - Safety in Design_WQCP.docx [Update to show User's file]                         Calibre Consulting (Aust) Pty Ltd
Log in to download the original file

16-001014-02A (Ultimate SCMMP).pdf · 14.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.