Treatment Device / Property Inspection Inspection Frequency Corrective Action1
Check 80% vegetation cover on batters and
Re‐establish vegetation using thriving vegetation within the asset
in water up to 300mm deep
Check that the average plant height is >
Vegetation Monitor plant growth where necessary
500mm
Check that plants are healthy and free If problem persists seek advice from a horticulturalist as per WBD’s
from significant disease. Rectifying Vegetated Stormwater Assets (2012).
Weeds2 Remove and control weed species. If problem is reoccurring increase
Check that weed cover is less than 10%
(emergent, floating or submerged) maintenance frequency for weed removal over a period
Undertake filling, profiling, and (if necessary) replanting using hand
Undertake mosquito testing ‐ 1 larvae per
Mosquitoes tools or light machinery. If problem persists refer to WBD’s
2 ladle dips (300mL ladle)
Rectifying Vegetated Stormwater Assets (2012).
Fertiliser3 Check for fertiliser on banks of WQCP Remove where fertiliser has not been specifically scheduled
Remove using rakes or specialist machinery.
If algal mats exceed 10%, the need to identify the source of the
Check that cover of algal mats does not Quarterly during dry season problem is required – refer to WBD’s Rectifying Vegetated
Algal Mats exceed 10% on two consecutive and every two months Stormwater Assets (2012)
inspections during wet seasons ‐ As high nutrient concentrations into the WQCP can result in
excessive algal mats, check upstream device (and clean out where
necessary), implement catchment management solutions.
Check that the water is clear, that is
turbidity is such that the floor of the pond Identify problem as per WBD’s Rectifying Vegetated Stormwater
can be seen at 0.75m depth Assets (2012) and implement necessary action:
Check for algal blooms ‐ Restrict access to WQCP using signage, public notification to
Check that macrophyte coverage to be prevent health risks (note basin area is fully fenced and separated
above 50% of the WQCP water surface. from public access)
Cyanobacterial Blooms If above indicators for cyanobacterial ‐ If low vegetation cover, immediately re‐establish. Replant with
blooms reveals non‐performance, water well‐established, dense vegetation.
quality testing is required. Performance ‐ If high nutrient concentrations in WQCP remove sediments, dry
indicator is ≤500cells/mL of Microcystis out WQCP for 1‐2weeks to destroy algae, remove nutrient source,
aeruginosa or biovolume equivalent replant if necessary.
≤0.04mm3/mL combined total of
cyanobacteria.
* Significant Rain Event defined as a 24 hour period with rainfall greater than 100mm, or shorter period with an average rainfall intensity greater than 50mm/hour.
1. Maintenance Requirements are based on Water by Designs, Maintaining Vegetated Stormwater Assets (2012) and Rectifying Vegetated Stormwater Assets (2012). Refer to these documents for further details.
2. Refer to latest version of HumeGard Maintenance Guide for details of inspection and maintenance procedures.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.