SUMMARY
Northbrook Corporation Pty Ltd commissioned Gilbert & Sutherland
Pty Ltd (G&S)to prepare a conceptual Groundwater Assessment
and Management Plan for the proposed Noosa on Weyba
development, Noosaville, Queensland.
A total of 15 groundwater bores were constructed across the
Hofmann Land by Golder Associates in 2007, however some of
these have since been damaged or destroyed. Our initial site
inspection located 13 existing bores suitable for groundwater
monitoring. No existing groundwater bores were located on the
Northbrook land. To augment the existing monitoring bore network
on the Hofmann land and establish a monitoring network on the
Northbrook land, G&S installed a total of six (6)additional
groundwater bores.
Six (6)rounds of groundwater monitoring were conducted at the site
from March to June 2012 and the collected data used to prepare a
conceptual groundwater model using the USGS groundwater
modelling package MODFLOW. The model was used to
conceptualise the existing groundwater environment and predict the
likely impacts of the proposed development.
Groundwater impacts predicted during the construction phase are
limited to the impacts of groundwater drawdown during trenching/
excavation works. The results of this assessment indicate that
where groundwater drawdown occurs, the lateral extent will vary
between 20m and 1,281 m. The larger drawdown extents are
predicted to occur in areas of the site where Tenosols (sandy soils)
have been identified. Whilst Hooghoudt’s equation predicts the
lateral extent of drawdown to extend up to 1,281 m in these soil
types, in reality, the true extent of drawdown will be limited to the
extent of this soil type.
Instances of groundwater drawdown are unlikely to be prolonged
with excavations such as services trenches excavated and
backfilled on a progressive basis. The extent of groundwater
drawdown calculated in this report is based on a scenario where no
mitigation measures are in place. Implementation of mitigation
measures such as those described in the attached Groundwater
1 0838_GWA_ELH2F.DOCX I NOOSA ON WEYBA I NORTHBROOK CORPORATION PTY LTD _
GROUNDWATER ASSESSMENT 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 17 of 37 Appendix 15 - Groundwater Assessment MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 60.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.