NOOSA COUNCIL IDAS Development Application Decision Notice                                                  6 of 12


Roof Water & Stormwater Drainage
37.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
      storage 3000 litres per attached dwelling/unit) that is installed to ensure water from the tank is used for
      external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
      swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
      rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
      (QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
      building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
      for Building Works / Operational Works approval and any overflow shall be directed to the stormwater
      drainage system.

38.   All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
      collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
      drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
      system in Duke Street. Plans of the drainage design shall be prepared by a Registered Professional Civil
      Engineer and submitted to Council prior to obtaining a Development Permit for Operational Works.
      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street drainage
      system at any one location is 25 litres/second.
39.   A grated drain shall be provided across the access driveway within the site adjacent to the street
      boundary to collect runoff from the manoeuvring area and the access driveway.

40.   All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
41.   The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
42.   The site shall be connected to Council’s existing town water supply and be constructed in accordance with
      Council’s standards and requirements at no cost to Council.

43.   Each individual water connection to the water reticulation system shall extend to the property boundary
      and be metered. All fees for the supply of water meters shall be paid to the Council.

44.   All water meters must be located outside the property boundary and in an easily assessable location to
      facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
      fences or locked gates. In this regard approval of the water meter configuration and location must be
      obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
      hydraulic drawings.

45.   For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
      served by:
      A single Body Corporate water meter to measure the total water consumption (including fire hose reels,
      but excluding fire hydrants and fire sprinkler systems), and
      Individual water meters to each tenement capable of being separately rated, and
      A fire service (fully testable single detector check with metered bypass), where applicable, for flows to fire
      hydrants and fire sprinkler systems (excluding fire hose reels).

Earthworks
46.   Earthworks required on site shall be carried out in accordance with Section 3.8 of Council’s Engineering
      Design Standards Manual and so as not to cause the additional ponding of water on any adjoining lands
      or the blockage of, or interference with, any natural watercourses.

47.   Excavation of the site and the construction of the proposed works shall not have any adverse affects on
      the stability of adjoining buildings and/or structures and/or services and/or lands. In this regard a
      Registered Professional Engineer Queensland shall supervise the excavation of the site and the
      construction of the new works to determine whether any additional measures are required to protect the
      stability of adjoining buildings and/or structures and/or services and/or lands.

48.   Earthworks carried out on site shall not affect the structural integrity of any of the existing fences that
      border the development site. Fences that are affected shall be replaced prior to the Building Certifier
      issuing the Certificate of Classification. In this regard any fences to be replaced shall be clearly shown on
      the plans submitted for Operational Works approval.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@400759ba\@[email protected]

Used in these records

About this file

File size
57 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00001045.001 [As Published].pdf · 57 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.