SITE BASED STORMWATER
MANAGEMENT PLAN
Revision B
Proposed Development at
36 & 38 DUKE STREET, SUNSHINE BEACH
for
Cambooya Pty Ltd
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 34 pages
Page 2
SITE BASED STORMWATER MANAGEMENT PLAN
Proposed Development at
36 & 38 DUKE STREET, SUNSHINE BEACH
for
Cambooya Pty Ltd
M3024E_DA1_SBSMP –Revision B
September 2023
JFP Urban Consultants Pty Ltd
Prepared by: C. Blair
Approved by: A. Fraser
Revision Date Details Prepared By Approved By
A 20/04/2023 For Authority Submission CB (RPEQ 19190) AF (RPEQ 5691)
B 18/09/2023 Information Request Response CB (RPEQ 19190) AF (RPEQ 5691)
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 3
TABLE OF CONTENTS
INTRODUCTION ....................................................................................................................... 1
1.1 OBJECTIVE & SCOPE ....................................................................................................... 1
1.2 INFORMATION REQUEST ITEMS ..................................................................................... 1
SITE CHARACTERISTICS ............................................................................................................ 3
2.1 LOCATION....................................................................................................................... 3
2.2 TOPOGRAPHY & DRAINAGE ........................................................................................... 3
STORMWATER QUANTITY ........................................................................................................ 6
3.1 LAWFUL POINT OF DISCHARGE ...................................................................................... 6
3.2 STORMWATER DISCHARGE STRATEGY ........................................................................... 6
3.3 RATIONAL METHOD CALCULATION ................................................................................ 6
3.4 PRE-DEVELOPMENT SITE XP-STORM .............................................................................. 7
3.4.1 CATCHMENT DATA ....................................................................................... 7
3.4.2 RAINFALL DATA ............................................................................................ 7
3.4.3 HYDROLOGICAL LOSSES ............................................................................... 7
3.4.4 BX FACTOR ................................................................................................... 7
3.4.5 EXISTING PEAK DISCHARGE .......................................................................... 7
3.5 POST-DEVELOPMENT SITE XP-STORM............................................................................ 8
3.5.1 CATCHMENT DATA ....................................................................................... 8
3.5.2 RAINFALL DATA, HYDROLOGICAL LOSSES & BX FACTOR .............................. 8
3.5.3 DETENTION TANK ......................................................................................... 9
3.5.4 POST-DEVELOPMENT PEAK DISCHARGE ...................................................... 9
3.5.5 DETENTION TANK RESULTS .......................................................................... 9
3.6 DOUGLAS LANE ROAD FLOW CALCULATION ................................................................ 10
3.6.1 PEAK FLOW CALCULATION ......................................................................... 10
3.6.2 ROAD CAPACITY CALCULATION .................................................................. 10
STORMWATER QUALITY ........................................................................................................ 11
4.1 CONSTRUCTION PHASE STORMWATER QUALITY MANAGEMENT ............................... 11
4.1.1 INTRODUCTION .......................................................................................... 11
4.1.2 POLLUTANTS .............................................................................................. 11
4.1.3 WATER QUALITY OBJECTIVES ..................................................................... 11
4.1.4 STORMWATER QUALITY MANAGEMENT STRATEGY .................................. 12
4.1.5 MONITORING & MAINTENANCE ................................................................ 12
4.1.6 RESPONSIBILITY & REPORTING ................................................................... 12
4.2 OPERATIONAL PHASE STORMWATER QUALITY MANAGEMENT .................................. 13
4.3 WATERWAY STABILITY MANAGEMENT ........................................................................ 13
CONCLUSION & RECOMMENDATIONS ................................................................................... 14
DISCLAIMER .......................................................................................................................... 15
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 4
APPENDICES .......................................................................................................................... 16 Appendix A – Existing Site Survey & Proposed Site Plans Appendix B – Spreadsheet Calculations Appendix C – XP-STORM Summary Appendix D – Stormwater Catchment Plans SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 5
INTRODUCTION
JFP Urban Consultants Pty Ltd has been commissioned by Cambooya Pty Ltd to compile this Site Based
Stormwater Management Plan (SBSMP) for the proposed development at 36 & 38 Duke Street,
Sunshine Beach (‘the site’). Noosa Council Application Number is MCU23/0070.
The site currently contains a restaurant located fronting Duke Street. It is understood that the proposal
is for a mixed-use development comprising the existing tenancy fronting Duke Street and five
residential apartments developed above. Refer to Appendix A for the survey of the existing site and for
the proposed development plans.
Revision B has been updated to address Stormwater Drainage issues (item 13) raised in the
Information Request dated 14th June 2023. Refer to Section 1.2 for summary responses.
1.1 OBJECTIVE & SCOPE
The design objectives for this report are:
Nominate the lawful point of discharge.
Ensure post-development peak flow rates are mitigated back to the pre-development peak flow
rates via onsite detention.
Confirm if the Water Quality Objectives (WQOs) in accordance with the State Planning Policy
(2017) is applicable for the site.
The scope of investigations undertaken for this report is as follows:
Nominate lawful point of discharge.
Undertake hydrological and hydraulic analysis for the site using the XP-STORM 1D. This analysis
includes the sizing of onsite detention to achieve peak flow mitigation.
Provide commentary regarding possible performance-based stormwater quality management
strategies for the operational phase of the development.
Based on the outcomes of the above investigations, this report provides recommendations, including
concept drawings for stormwater management. These recommendations should be incorporated into
future detailed design and subsequent construction documentation.
1.2 INFORMATION REQUEST ITEMS
Issue – Stormwater Drainage
The submitted documentation does not include sufficient information for Council to assess how
stormwater generated by the development will be controlled, collected, and discharged.
It is unclear what the proposed structure downstream from the proposed detention tank is and
how it will integrate into the proposed drainage system (indicated by a blue circle).
It is unclear how the proposed detention tank overflows during events up to, and including, a 1%
AEP event (volume, discharge rate).
It is unclear how the infiltration outlet of the detention tank will operate. Given the large
catchment area of the detention tank, Council is concerned the soil may become oversaturated
and the filtration rate of the soil will reduce which may adversely affect the overall drainage
system and the structural elements of the development.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |1
Page 6
It is unclear how the proposed field inlet in catchment D3 will function during a 1% AEP event.
Council recognise that this field inlet serves both the overflow from the detention tank and a small
catchment area. Council is concerned that during events up to, and including, a 1% AEP event this
pit may surcharge and direct additional runoff on to the footpath in the road reserve.
The discharge rate of the RHS kerb adapter is unclear. Council is unlikely to support a discharge
rate higher than 25 l/s during a 1% AEP event.
Information Required
13. Provide additional detail to address Council’s concerns. The additional detail must be prepared by a
suitably qualified person (RPEQ).
Note that the detail can be preliminary in nature but must be sufficiently detailed to demonstrate that
the stormwater system is conceptually functional.
RESPONSE:
The following responses are provided for each dot point raised:
The ‘blue circle’ is a manhole/roofwater pit. It conceptually shows a junction at which drainage
pipes change direction. The concept plans have been amended and further details can be provided
during detailed design as required.
The outflow from the tank is controlled via a 75mm diameter orifice. It limits 1% AEP site discharge
to 25L/s as requested in dot point #5. An overflow weir is proposed at RL 33.11m AHD to allow
overflow.
No infiltration is proposed. All outflows are directed to Duke Street kerb and channel.
Runoff from a majority of Catchment D3 will be collected by building’s roofwater system. The
proposed field inlet in Catchment D3 has been amended to a roofwater pit and it can be provided
with a bolt down cover so that it will not surcharge. The outflow pipe from the detention tank will
operate under head. This is consistent with standard building hydraulic design.
The discharge rate from site has been limited to 25L/s in a 1% AEP storm event. This has been
achieved by increasing detention volume and limiting outflows via 75mm diameter orifice.
Appropriate screens can be incorporated in detail design to minimise blockage of this orifice. Any
additional requirements can be conditioned.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |2
Page 7
SITE CHARACTERISTICS
2.1 LOCATION
The site is in the Noosa Shire Council local government area. The site has real property descriptions Lot
370 & 371 on RP48111 – more commonly known as 36 & 38 Duke Street, Sunshine Beach. It has
frontage to Duke Street to the south and Douglas Lane to the north; and currently contains a
restaurant fronting Duke Street. Refer to Figure 1 for aerial view.
The site is not identified to be affected by flooding or tidal influence.
Site
Figure 1 – Site Location (Source: Nearmap, August 2022)
2.2 TOPOGRAPHY & DRAINAGE
The site falls toward Duke Street at an average grade of 10%. A site visit was undertaken on 26th July
2022, and the following drainage patterns were observed.
The existing site appears to discharge roofwater to Duke Street via two kerb adapters located on
high side and low side of the site. Refer to Figure 2 and Figure 3.
No existing stormwater infrastructure was observed in the rear of the site. Surface flows from the
rear is expected run down the pathway adjacent to the existing building. Refer to Figure 4.
A road flow calculation has been undertaken on Douglas Lane to confirm up to and including a 1%
AEP external flows do not enter the site. Refer to Section 3.6.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |3
Page 8
Existing
restaurant
on site
Existing kerb
adapter, high side
Figure 2 – Existing High Side Kerb Adapter
Existing kerb
adapter, low side
Figure 3 – Existing Low Side Kerb Adapter
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |4
Page 9
Existing
building
Existing
pathway
Figure 4 – Rear of the Site, viewed from Douglas Lane
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |5
Page 10
STORMWATER QUANTITY
3.1 LAWFUL POINT OF DISCHARGE
The proposed lawful point of discharge is the kerb & channel on Duke Street. Currently there are two
kerb adapters fronting the site. It is proposed to utilise only the low side kerb adapter and upgrade as
required. The 1% AEP peak flow rate has been limited to 25L/s.
3.2 STORMWATER DISCHARGE STRATEGY
The fraction imperviousness increases due to the proposed development. To mitigate increase to peak
discharge rates an on-site detention tank is proposed. The tank is proposed to be located on ground
level at RL 30.26m AHD.
It is proposed to collect and convey a majority of the site runoff into the detention tank. Mitigated
flows are to be discharged on to Duke Street kerb & channel.
3.3 RATIONAL METHOD CALCULATION
The Rational Method Calculation has been undertaken for the pre-development site. Table 1 presents
the Rational Method catchment parameters. Refer to Drawings No. M3024E_DA1_SK01 in Appendix D
for the catchment plan. The fraction imperviousness has been estimated from the detailed survey
(included in Appendix A). The C10 has then been determined in accordance with Table 4.5.3 of the
QUDM (2016) and the time of concentration (Tc) based on the Standard Inlet Time in accordance with
Table 4.6.2 of the QUDM (2016).
Table 1 – Rational Method Calculation Parameters
Fraction
Catchment Area (ha) C10 Tc (mins)
Impervious
E1 0.0486 57% 0.82 8
Site specific 2016 rainfall intensities were obtained from Bureau of Meteorology (BOM). Table 2
presents the Rational Method peak flow rates. Further details included in Appendix B.
Table 2 – Rational Method Peak Flows
Rational Method Peak Flows (m³/s)
63% AEP 39% AEP 20% AEP 10% AEP 5% AEP 2% AEP 1% AEP
E1 0.010 0.013 0.018 0.022 0.026 0.033 0.037
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |6
Page 11
3.4 PRE-DEVELOPMENT SITE XP-STORM
A peak flow analysis has been undertaken using the XP-STORM version 2021.3 for sizing the detention
tank. The pre-development site was modelled using a single node and peak flows verified against the
Rational Method Calculation.
3.4.1 CATCHMENT DATA
Table 3 presents the catchment modelled in XP-STORM. Refer to Drawings No. M3024E_DA1_SK01 in
Appendix D for the catchment plan.
Table 3 – Pre-Development Catchment Data
Fraction Vectored Slope
Catchment Area (ha)
Impervious (%)
E1 0.0486 57% 10%
3.4.2 RAINFALL DATA
The site specific 2016 rainfall intensities obtained from BOM coupled Australian Rainfall & Runoff (AR&R)
1987 temporal patterns for zone 3 have been used to generate peak flow hydrographs in XP-STORM.
3.4.3 HYDROLOGICAL LOSSES
The following initial loss, continuous loss and Manning’s n values have been adopted for the
hydrological modelling. They are within the ranges recommended in the AR&R (1987) for Southeast
Queensland.
Table 4 – Hydrological Losses
Continuing Loss
AEP Area Type Initial Loss (mm) Manning’s n
(mm/hr)
Impervious Area 0 0 0.014
63% to 1%
Pervious Area 15 2 0.07
3.4.4 BX FACTOR
A Bx factor of 1.8 has been used across all AEPs modelled.
3.4.5 EXISTING PEAK DISCHARGE
The XP-STORM hydrology was run for the standard AEPs from a 63% AEP to a 1% AEP and 15 to 180-
minute standard durations. Table 5 presents pre-development site peak flows.
Table 5 – Pre-Development Peak Flows
Pre-Development Peak Flows (m³/s)
63% AEP 39% AEP 20% AEP 10% AEP 5% AEP 2% AEP 1% AEP
Rational Calc 0.010 0.013 0.018 0.022 0.026 0.033 0.037
XP-STORM 0.012 0.017 0.021 0.027 0.032 0.034 0.038
Variance +0.002 +0.004 +0.003 +0.005 +0.006 +0.001 +0.001
The XP-STORM peak flows are generally similar to the Rational Method Calculation, particularly for the
larger 1% and 2% AEP storms. On that basis, the XP-STORM peak flow rates have been used for the
peak flow and detention tank analysis for this site.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |7
Page 12
3.5 POST-DEVELOPMENT SITE XP-STORM
3.5.1 CATCHMENT DATA
Table 6 presents the post-development catchment details. Drawing No. M3024E_DA1_SK02 in
Appendix D presents the catchment delineation.
Table 6 – Post-Development Catchment Data
Fraction Vectored Slope
Catchment Area (ha)
Impervious (%)
D1 0.0335 100% 10%
D2 0.0121 66% 10%
D3 0.0030 100% 10%
Total 0.0486 92% 10%
The following catchment arrangements have been modelled:
5% AEP from catchment D1 has been modelled to enter the detention tank. Larger flows bypass
detention.
1% AEP from catchment D2 has been modelled to enter the detention tank.
Catchment D3 bypasses the detention tank.
Figure 5 presents the XP-STORM layout for the post-development site.
Figure 5 – Post-Development XP-STORM Layout
3.5.2 RAINFALL DATA, HYDROLOGICAL LOSSES & BX FACTOR
As per the pre-development scenario.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |8
Page 13
3.5.3 DETENTION TANK
Table 7 presents the detention tank parameters modelled. Refer to Appendix C for the stage vs area
relationship. Re-analysis will be required if the stage-area relationship is significantly altered.
Table 7 – Detention Tank Details
Parameter Value
Detention Tank Dimensions (m) 4.5m² surface area x 3m deep (min)
Available Volume (m³) 13.5
Available Depth (m) 3.0 (min)
Detention Tank IL (m AHD) 30.26
Orifice Outlet 75mm dia at IL 30.26m AHD
Weir Outlet 1200mm weir at RL 33.11m AHD
3.5.4 POST-DEVELOPMENT PEAK DISCHARGE
The XP-STORM was run for 63% AEP to 1% AEP storms with 15 to 180-minute standard durations.
Table 8 presents the peak flow results.
Table 8 – Pre & Post-Development Peak Flows (XP-STORM)
Peak Flow Results (m³/s)
63% AEP 39% AEP 20% AEP 10% AEP 5% AEP 2% AEP 1% AEP
Post-Dev. 0.012 0.014 0.016 0.018 0.021 0.022 0.025
Pre-Dev. 0.012 0.017 0.021 0.027 0.032 0.034 0.038
Variance 0 -0.003 -0.005 -0.009 -0.011 -0.012 -0.013
The results show peak flow rates are not increased. Moreover, the 1% AEP flow is limited to 25L/s
(0.025m³/s).
3.5.5 DETENTION TANK RESULTS
Table 9 presents the detention tank performance. As can be seen, the 1% AEP volume is within the
nominated minimum tank volume.
Table 9 – Detention Tank Results
63% AEP 39% AEP 20% AEP 10% AEP 5% AEP 2% AEP 1% AEP
Tank Inflow
0.017 0.022 0.026 0.030 0.034 0.035 0.037
(m³/s)
Tank Outflow
0.011 0.013 0.015 0.017 0.019 0.021 0.023
(m³/s)
Detention
4.1 5.5 7.0 8.7 10.3 11.4 12.9
Volume (m³)
Depth of
0.90 1.22 1.56 1.93 2.29 2.53 2.85
Water (m)
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |9
Page 14
3.6 DOUGLAS LANE ROAD FLOW CALCULATION
A road flow capacity assessment has been undertaken to confirm that the external flows on Douglas
Lane do not enter the site.
3.6.1 PEAK FLOW CALCULATION
Refer to Figure 6 for the external catchment delineation and Table 10 for peak flow rates calculated
using the Rational Method. Refer to Appendix B for additional details.
External
Catchment
0.13ha
Manning’s
Section
Figure 6 – External Catchment to Douglas Lane
Table 10 – External Catchment Peak Flows
63% AEP 39% AEP 20% AEP 10% AEP 5% AEP 2% AEP 1% AEP
Peak Flow (m³/s) 0.030 0.040 0.055 0.068 0.081 0.103 0.113
3.6.2 ROAD CAPACITY CALCULATION
The Manning’s Equation has been used to undertake a road flow calculation on Douglas Lane. Refer to
Figure 6 above for the cross-section location. The longitudinal grade on Douglas Lane fronting the site
is approximately 8% and a surface roughness value of 0.015 was adopted for the pavement.
The results in Table 11 show the flows do not overtop the kerb, which is approximately 120mm high.
Refer to Appendix B for further calculation details.
Table 11 – Manning’s Equation Calculation
Max Road Flow Depth
1% AEP Flow (m³/s) Velocity (m/s) DV Product (m²/s)
(mm)
0.113 42 1.54 0.07
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 10
Page 15
STORMWATER QUALITY
4.1 CONSTRUCTION PHASE STORMWATER QUALITY MANAGEMENT
4.1.1 INTRODUCTION
This section provides conceptual stormwater quality management strategies for construction phase.
These strategies are applicable for all stages of the development. No modelling has been undertaken
for the construction phase stormwater quality management. Detailed Erosion and Sediment Control
Plans will be prepared during detailed design phase and implemented during construction.
4.1.2 POLLUTANTS
Typical pollutants generated during the construction phase of an urban development are shown in
Table 12. These based on Table C4.1 BCC’s Subdivision & Development Guidelines Part C Section 4.1.1
(2008).
Table 12 – Construction Phase Pollutants
Pollutant Potential Source
Litter Paper, construction packaging, food packaging, cement bags, off-cuts.
Sediment Unprotected exposed soils and stockpiles during earthworks and building works.
Hydrocarbons Fuel/oil spills, leaks from construction equipment, and temporary car park areas.
Toxic
Cement Slurry, asphalt primer, solvents, cleaning agents, and washwaters etc.
Materials
pH altering
Cement slurry, acid sulfate soils, and washwaters
substances
4.1.3 WATER QUALITY OBJECTIVES
It is recommended that the amount of runoff crossing and leaving the site is kept to a minimum during
the construction phase to restrict soil erosion and mobilisation of sediments and pollutants through
and off the site. Table 13 presents an extract from Table A, Appendix 2 of the State Planning Policy
(2017) objectives for construction phase stormwater quality management
Table 13 – Construction Phase Performance Criteria
Issue Desired Outcomes
1. Stage clearing and construction works to minimise the area of exposed soil
at any one time.
2. Effectively cover or stabilise exposed soils prior to predicted rainfall.
Erosion control
3. Prior to completion of works for the development, and prior to removal of
sediment controls, all site surfaces must be effectively stabilised using
methods which will achieve effective short-term stabilisation.
1. Direct runoff from exposed site soils to sediment controls that are
appropriate to the extent of disturbance and level of erosion risk.
2. All exposed areas greater than 2500m² must be provided with sediment
Sediment
controls which are designed, implemented and maintained to a standard
Control
which would achieve at least 80% of the average annual runoff volume of
the contributing catchment treated (i.e. 80% hydrological effectiveness) to
50mg/L Total Suspended Solids (TSS) or less, and pH in the range (6.5–8.5).
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 11
Page 16
4.1.4 STORMWATER QUALITY MANAGEMENT STRATEGY
An erosion and sediment control management plan that is endorsed by an CPESC or RPEQ will be
prepared and implemented during construction phase. Erosion and sediment control measures may
include, but not limited to, devices such as:
catch drains,
diversion drains,
silt fences, and
construction entry/exit pads.
4.1.5 MONITORING & MAINTENANCE
The general requirement of monitoring during the construction phase will be:
Work activities to be restricted to designated construction areas.
Earthworks and site clearing to be undertaken in accordance with the Erosion and Sediment
Control Plans prepared during detailed design phase.
Erosion and sediment control devices to be constructed in accordance with the Erosion and
Sediment Control Plans prepared during detailed design phase.
Inspect sediment fences and erosion and sediment control structures/devices on a weekly basis as
well as after any rain event exceeding 25mm in 24hrs.
Stormwater discharges from the site are not to have any adverse effect on the downstream
environment.
Monitor and record of the performance of the drainage control devices including water quality
testing where required.
Any failure in the stormwater system to be immediately rectified to prevent uncontrolled
discharge from the site.
Any failure to the stormwater system causing damage to surroundings should implement
immediate remedial work to the damaged area.
4.1.6 RESPONSIBILITY & REPORTING
The contractor shall be responsible for monitoring the performance of all drainage control and
erosion and sediment control devices.
Records of any failures to devices should be kept and reported to the Construction Manager.
Regular inspections of the devices shall be reported to the Construction Manager.
Inspections of the devices after heavy rainfall shall be reported to the Construction Manager.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 12
Page 17
4.2 OPERATIONAL PHASE STORMWATER QUALITY MANAGEMENT
The development footprint is 486m² which is less than 2,500m². Therefore, the site does not trigger
compliance with the State Planning Policy (2017) for stormwater quality management and meeting the
required Water Quality Objectives (WQOs). The development is also not discharging into ‘High
Ecological Value’ waters. On that basis, no conventional stormwater improvement devices such as
bioretention are proposed and MUSIC modelling has not been undertaken for the site.
While no active stormwater treatment measures such as bioretention is proposed, the site will have
some passive stormwater quality treatment measures. For instance, most of the site is covered by the
building footprint and most of the building runoff is directed into a detention tank. Most of the gross
pollutants such as tree leaves and visible rubbish will be captured in the roof gutters. Smaller gross
pollutants and Suspended Solids that travel through the roof drainage system will enter the detention
tank where runoff will pond for a period of time allowing the pollutants to settle into the bottom of
the bank. Periodic maintenance of the roof drainage system and the detention tank will ensure most
of the gross pollutants and Suspended Solids are captured within the site prior to discharging into the
downstream drainage network.
The landscaping proposed within the site will also provide water quality benefit to runoff that is
directed to them. The vegetation will capture primary pollutants and the soil underneath will provide
some level of nutrient treatment.
4.3 WATERWAY STABILITY MANAGEMENT
The waterway stability management in accordance with the State Planning Policy (2017) is not
applicable for this site, as the site flows are connected to an urban underground drainage network
which then discharges into tidal waters.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 13
Page 18
CONCLUSION & RECOMMENDATIONS
JFP Urban Consultants Pty Ltd has prepared this Site Based Stormwater Management Plan for the
proposed development at 36 & 38 Duke Street, Sunshine Beach. The analyses presented in this report
achieve the following outcomes:
The outcomes of the stormwater analyses are:
The proposed lawful point of discharge is the kerb & channel on Duke Street and 1% AEP discharge
is 25L/s.
On-site detention is proposed. The 1% AEP detention volume is 12.9m³.
Douglas Lane has adequate capacity to convey 1% AEP external catchment flows so they do not
enter the site.
Erosion & sediment control measures are to be finalised during detailed design and incorporated
in the construction phase.
As the site area is less than 2500m² the development does not trigger the State Planning Policy
(2017) for operational phase stormwater quality management and therefore stormwater quality
treatment devices such as bioretention is not required. However, the site’s internal drainage
system and the landscaping areas will provide some level of stormwater quality treatment,
particularly for the gross pollutants and Suspended Solids.
It is recommended that the management strategies presented in this report are incorporated into
future detailed design and subsequent construction. While variations to the concepts are allowed, the
design objectives are to be maintained.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 14
Page 19
DISCLAIMER
This report has been prepared for the purpose and exclusive use of Cambooya Pty Ltd as an
investigation into the stormwater management issues related for the proposed development of the
land described in the report. The information presented in this report is not to be used for any other
purpose or by any other person or corporation.
JFP Urban Consultants Pty Ltd accepts no responsibility for any loss or damage suffered howsoever
arising to any person or corporation who may use or rely on this report without further input and/or
advice from JFP Urban Consultants Pty Ltd.
The investigations, calculations, analysis and recommendations presented in this report rely on
information sourced from third-parties. JFP Urban Consultants Pty Ltd accepts no responsibility for the
accuracy of the information sourced from third-parties.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 15
Page 20
APPENDICES
Appendix A – Existing Site Survey & Proposed Site Plans
Appendix B – Spreadsheet Calculations
Appendix C – XP-STORM Summary
Appendix D – Stormwater Catchment Plans
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 16
Page 21
APPENDIX A – EXISTING SITE SURVEY & PROPOSED SITE PLANS SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 22
[5 STORMWATER GRATE
6) STORMWATER MANHOLE
G
SEWER MANHOLE
ELECTRICITY JUNCTION BOX
TELSTRA PIT
WATER METER
HYDRANT
STOP VALVE
POWER POLE
UIGHT POLE
BENCH MARK
exregiz®
®
LINETYPE LEGEND
BANK BOTTOM
BANK TOP
BATTER
CROWN
currer
= GRAVEL
‘BITUMEN
KERB
CONCRETE
ELECTRICAL
WATER
awiPoot
SEWER
DRAINAGE
TREELINE
GARDEN
T TELSTRA
——— sutone
—------ PAVING:
POE RETAINING WALL
WALL
a CUAROR AL
Fence
Boy
‘MAJOR CONTOUR
MINOR CONTOUR,
cP
SP120994
0 2 4 6 8
cP
SP176872
ES
ROR
RS
SS
SOS
Re
Ss
ey
>
YY
AS
8
‘
30
us
10
Ss
x
12
Scale 1:200 - Lengths are in Metres
14
DENOTES GRAVEL
DENOTES CONCRETE
DENOTES BUILDING
DENOTES aITUMEN
DENOTES PAVING
MAX WATTERSON
+ASSOCIATES
CONSULTING SURVEYORS
& PLANNERS
12. Maple Street
PO Box 639
Cooroy Qld 4563,
Ph. (07) 54426121
Fax. (07) 54425125
Email [email protected]
Client:
CAMBOOYA
PTY LTD
Project:
DETAIL AND
CONTOUR PLAN OF
LOTS 370 & 371 ON
RP48111.
LOCAL GOVT: NOOSA S.C.
LOCALITY: SUNSHINE BEACH
Scale: 1:200 Plan 4 of 4
Datum: AHD Date: 31-08-23
Origin: pee27 .
Cont 2s . Ref.
font.nt: 0.25m
22-5703AB
NOTE:
This plan has been prepared for building
design purposes only.
Underground services not located except
where evident on surface.
Page 23
A B C D E A B C D E
DA15 DA15 DA15 DA16 DA16 DA15 DA15 DA15 DA16 DA16
36 36
S 35 34 35 34
S
60
D O U G L A S 14980
L A N E 48
D O U G L A S L A N E
60 14980 45
1020 7770 6190
4390 10590
BOOSTER
REFUSE
HIGH POINT
RED HATCH INDICATES PLANTING
ZONE TO BE LESS THAN 0.6m
2x 1100L BINS HIGH & NO SOLID OBSTRUCTIONS
35 35
5500
UP
7537
7537
7537
7537
300
5400
34 34
2500
1200
MB4
34 34 V1
300
2500
700
GRATED DRAIN
13
12
11
10
9
8
7
6
5
4
3
2
1
OUTFLOW
8
7
6
5
4
3
2
1
UP
UP
33 33
TANK
2780
J J J J
DA23 DA23
6900
DA23 DA23
STAIR STAIR
14
15
16
17
18
19
20
21
10
17
18
19
20
21
9
LIFT SCREEN FOR LIFT
33 MECHANICAL 33
300
EXHAUST DUCT 1:
9460
10
UP C1
11450
EXTENT OF ENTRY RAMP
SHOWN DASHED
MECH EXHAUST DUCT
32
2500
I I I I
DA23 DA23 DA23 DA23
R1
5900
500 5400 6300 2400
2500
32
R2
CARPARK
300
GROUND FLOOR PUBLIC LOBBY
C2
22650
2600
H H H H
AMENITIES
24630
24630
24630
24630
DA23 DA23 DA23 5400 9200 DA23
19870
R3
31
TURN
5800
ZONE
2400
R4
BIKE
G G G 2500 300 1200 2600 2600 300 2500 G
DA23 DA23 DA23 DA23
2300
15170
BIKE
R5 C3
MB1
1200
13180
31 POOL PUMP &
1 x BIKES
POOL PUMP &
900
FILTER
FILTER
MB3 MB2
5400
POOL SHELL POOL SHELL
SUBSTRATE SUBSTRATE
F TENANCY 01 TENANCY 02 F F F
11
DA23 DA23 DA23 2 x BIKES DA23
m
2
1980
1980
PLANTER
30
20
20
OUTDOOR DINING OUTDOOR DINING
20
20
20
20
20
20
OUTDOOR BUSINESS AREA OUTDOOR BUSINESS AREA
16 m2 15 m2
11990 2990 AWNING BELOW 11990
60 14980 48 60 14980 48
S
A B C D E A B C D E
DA15 DA15 DA15 DA16 DA16 DA15 DA15 DA15 DA16 DA16
30 30
01 FLOOR PLAN DUKE STREET 02 FLOOR PLAN LEVEL 1 / DOUGLAS LANE
1:100 1:100
PROPOSED MIXED USE DEVELOPMENT,
north
CAMBOOYA PTY LTD DEVELOPMENT APPROVAL
scale : 1:100 @A1 1:200 @A3
DUKE STREET & DOUGLAS LANE issue : 13 date : 08-09-23
36 - 38 DUKE STREET, SUNSHINE BEACH FLOOR PLANS 7252-DA06
A R CHIT E CT UR E | L A NDS CA P E | INT E R IOR | P ROJECT MA NA G E ME NT
7252-25-Duke St Option10.pln Friday, 8 September 2023 3:01 pm The designs, drawings and specification are copyright and always remain the property of Blackburne Jackson Design Pty Ltd.
GSPublisherVersion 1259.0.72.0
Page 24
A B C D E
DA15 DA15 DA15 DA16 DA16
1080 12070 1938
5100 6970
7237
7237
CONCRETE LID OVER
ISOLATED STAIR
LIFT LID TO SIT UNDER ROOF
SHEETING 12.0m HEIGHT LIMIT PROJECTION
EXTENT OF METAL ROOF ABOVE NATURAL GROUND
SHEETING AS INDICATED
3080
J J
DA23 DA23
LIFT OVER
2000
RUN
(BELOW)
3038
6o FALL
1000
I I
DA23 DA23
15990
17250
17250
8450
H H
DA23 DA23
3720
G G
1260
DA23 DA23
1100 5520 5530
1000 12150 1938
7700
7700
F F
DA23 DA23
A B C D E
DA15 DA15 DA15 DA16 DA16
01 ROOF PLAN 02 HEIGHT PLANE PROJECTION
1:100 1:50
PROPOSED MIXED USE DEVELOPMENT,
north
CAMBOOYA PTY LTD DEVELOPMENT APPROVAL
scale : 1:100 @A1 1:200 @A3
ROOF PLAN & HEIGHT PLANE issue : 08 date : 08-09-23
36 - 38 DUKE STREET, SUNSHINE BEACH PROJECTION 7252-DA08
A R CHIT E CT UR E | L A NDS CA P E | INT E R IOR | P ROJECT MA NA G E ME NT
7252-25-Duke St Option10.pln Friday, 8 September 2023 3:01 pm The designs, drawings and specification are copyright and always remain the property of Blackburne Jackson Design Pty Ltd.
GSPublisherVersion 1259.0.72.0
Page 25
BOUNDARY
BOUNDARY
BOUNDARY
BOUNDARY
EXHAUST DUCTING TO BE
UNDER HEIGHT LIMIT PLANE
DOUGLAS DUKE DOUGLAS DUKE
LANE 12m HEIGHT LIMIT DA
SHED STREET LANE nom. LIFT 12m HEIGHT LIMIT DA
SHED STREET
OVERRUN TO
FUTURE DETAIL
nom. LIFT OVERRUN TO
FUTURE DETAIL STAIR LID
ROOF ROOF
RL 42.960 RL 42.960
STAIR BALC
2900
2900
SCREEN TO CONCEAL APT 03 APT 03 BALC
EXHAUST DUCTING
STAIR
LEVEL 3 LEVEL 3
RL 40.060 RL 40.060
LIFT
3100
3100
APT 01 BALC APT 01
HARDSTAND LEVELS TO CIVIL
ENGINEER'S DRAWING
NO GAPS TO
BALUSTRADE -
HARDSTAND LEVELS TO CIVIL
ENGINEER'S DRAWING BALC
SPLASH PROOF
LEVEL 2 LEVEL 2
RL 36.960 RL 36.960
POOL PLANTER
PLANTER
3100
3100
CAR PARKING CONCRETE
CAR PARKING CONCRETE
AWNING OVER
AWNING OVER FOOTPATH
FOOTPATH
DOUGLAS LANE DOUGLAS LANE
RL 33.860 RL 33.860
ENCLOSED ENCLOSED
UNDERCROFT UNDERCROFT
nom. TANKING & nom. TANKING &
TENANCY TENANCY
3600
3600
WATERPROOF MEMBRANE TO WATERPROOF MEMBRANE TO nom. TANKING &
CIVIL ENGINEER'S DETAIL nom. TANKING &
WATERPROOF MEMBRANE TO [LAYOUT AS PER 7252_DA13] FOOTPATH CIVIL ENGINEER'S DETAIL WATERPROOF [LAYOUT AS PER 7252_DA13] FOOTPATH
MEMBRANE TO CIVIL
CIVIL ENGINEER'S DETAIL
ENGINEER'S DETAIL
DUKE STREET DUKE STREET
RL 30.260 RL 30.260
NATURAL GROUND LINE DASHED
PROPOSED GROUND LINE PROPOSED GROUND LINE
01 A SECTION 02 B SECTION
1:100 1:100
BOUNDARY
BOUNDARY
DOUGLAS 8047
DUKE
LANE ROOF APEX 12m HEIGHT LIMIT DASHED STREET
RL 44.734
SLAB
SLAB EXTENSION AS EXTENSION AS
SUNSHADE FOR LEVEL SUNSHADE FOR
BELOW LEVEL BELOW
ROOF ROOF APEX
RL 42.960 RL 42.960
DROP SLAB TO PROTECT
EXTERNAL ACCESS FROM EXTERNAL
WEATHER
BALC
APT ACCESS
2900
APT 03
2400
SLAB EXTENSION AS 9950
SUNSHADE FOR LEVEL
BELOW
LEVEL 3
RL 40.060
11400
DROP SLAB TO PROTECT
EXTERNAL ACCESS FROM
WEATHER
3100
EXTERNAL
APT 01
2400
APT ACCESS 9950
BALC
12000
LEVEL 2
RL 36.960
HARDSTAND LEVELS TO CIVIL
ENGINEER'S DRAWING PLANTER
CONCRETE
2755
CAR PARKING
2400
2537
3100
AWNING OVER
FOOTPATH
LEVELS TO CIVIL ENGINEER'S DRAWINGS
HIGHEST POINT
DOUGLAS LANE RL 34.310
RL 33.860
NATURAL GROUND
RL 33.334
BATHROOM
TENANCY
3600
GROUND FLOOR
nom. TANKING &
WATERPROOF MEMBRANE
PUBLIC LOBBY [LAYOUT AS PER 7252_DA13] FOOTPATH
TO CIVIL ENGINEER'S DETAIL NATURAL GROUND
RL 30.960
DUKE STREET
RL 30.260
NATURAL GROUND LINE DASHED
PROPOSED GROUND LINE
03 C SECTION
1:100
PROPOSED MIXED USE DEVELOPMENT,
north
CAMBOOYA PTY LTD DEVELOPMENT APPROVAL
scale : 1:100 @A1 1:200 @A3
issue : 09 date : 08-09-23
36 - 38 DUKE STREET, SUNSHINE BEACH SECTIONS 7252-DA15
A R CHIT E CT UR E | L A NDS CA P E | INT E R IOR | P ROJECT MA NA G E ME NT
7252-25-Duke St Option10.pln Friday, 8 September 2023 3:01 pm The designs, drawings and specification are copyright and always remain the property of Blackburne Jackson Design Pty Ltd.
GSPublisherVersion 1259.0.72.0
Page 26
APPENDIX B – RATIONAL METHOD CALCULATION Rational Method Calculation – Site Rational Method Calculation – External Catchment (Douglas Lane) Manning’s Calculation – Douglas Lane SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 27
RATIONAL METHOD CALCULATION – SITE
Catchment Details EXISTING SITE PROPOSED SITE
Area (ha) 0.0486 0.0486
Impervious Area (ha) 0.0277 0.044
Fraction Impervious (%) 57% 92%
1
I60 (mm/hr) 75.2 75.2
C1 0.656 0.70
C2 0.70 0.75
C5 0.78 0.84
C10 0.82 0.88
C20 0.86 0.92
C50 0.94 1.00
C100 0.98 1.00
Time of Concentration (min)
Method Tc
Catchment
EXISTING SITE Standard inlet time, catchment slope ~14% 8
PROPOSED SITE Standard inlet time, mostly paved/impervious areas 5
Rainfall Intensities (mm/hr)
Catchment 1yr ARI 2yr ARI 5yr ARI 10yr ARI 20yr ARI 50yr ARI 100yr ARI
EXISTING SITE 111 139 168 196 223 257 282
PROPOSED SITE 125 158 193 227 259 301 333
Stormwater Quantities (m3/s)
Catchment 1yr ARI 2yr ARI 5yr ARI 10yr ARI 20yr ARI 50yr ARI 100yr ARI
EXISTING SITE 0.010 0.013 0.018 0.022 0.026 0.033 0.037
PROPOSED SITE 0.012 0.016 0.022 0.027 0.032 0.041 0.045
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 28
RATIONAL METHOD CALCULATION – EXTERNAL
CATCHMENT (DOUGLAS LANE)
EXTERNAL
Catchment Details
CATCHMENT
Area (ha) 0.1302
Impervious Area (ha) 0.1042
Fraction Impervious (%) 80%
1
I60 (mm/hr) 75.2
C1 0.70
C2 0.74
C5 0.83
C10 0.87
C20 0.91
C50 1.00
C100 1.00
Time of Concentration (min)
Catchment Method Tc
EXTERNAL CATCHMENT Standard inlet time, mostly paved/impervious areas 6
Rainfall Intensities (mm/hr)
Catchment 1yr ARI 2yr ARI 5yr ARI 10yr ARI 20yr ARI 50yr ARI 100yr ARI
EXTERNAL CATCHMENT 120 151 184 215 245 284 313
Stormwater Quantities (m3/s)
Catchment 1yr ARI 2yr ARI 5yr ARI 10yr ARI 20yr ARI 50yr ARI 100yr ARI
EXTERNAL CATCHMENT 0.030 0.040 0.055 0.068 0.081 0.103 0.113
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 29
MANNING’S CALCULATION – DOUGLAS LANE
Cross Sec tion Details 1 % AEP Flow
P oint CH Z n wA wP n x wA
1 0.00 0.080 0.015
2 0.00 0.000 0.015 0.00 0.04 0.00
3 0.50 0.012 0.015 0.02 0.50 0.00
4 1.31 0.027 0.015 0.02 0.80 0.00
5 2.06 0.021 0.015 0.01 0.75 0.00
6 2.61 0.018 0.015 0.01 0.56 0.00
7 2.88 0.017 0.015 0.01 0.26 0.00
8 3.50 0.073 0.015 0.00 0.29 0.00
9 4.67 0.089 0.015
wA wP n x wA
TO TAL 0.073 3.207 0.001
Slope (m/m)
0.08 R n Q
0.023 0.015 0.113
Design Flow (m³/s) 0.113
WSL (m) 0.042
Results
Channel Flow (m³/s) 0.113
Velocity (m/s) 1.54
Max. Depth (m) 0.042
DV Product (m²/s) 0.07
0.10
0.09
0.08
0.07
0.06
0.05 Surface
1% AEP Flow
0.04
0.03
0.02
0.01
0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Chainage (m)
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 30
APPENDIX C – XP-STORM SUMMARY Pre-Development Site Discharge (XP-STORM hydrographs) Post-Development Site Discharge (XP-STORM hydrographs) Detention Tank Stage-Area-Volume SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 31
PRE-DEVELOPMENT SITE DISCHARGE POST-DEVELOPMENT SITE DISCHARGE SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 32
JFP URBAN CONSULTANTS = JFOP URBANCONSULTANTS DETENTION TANK STAGE-AREA-VOLUME RL (m AHD) Height (m) Area (m?) Area (ha) Incremental Vol (m3?) Accum. Vol (m3) 4.50 0.00045 0 0.0 4.50 0.00045 r 0.450 0.5 4.50 0.00045 r 0.450 0.9 4.50 0.00045 r 0.450 14 4.50 0.00045 r 0.450 18 4.50 0.00045 r 0.450 2.3 4.50 0.00045 r 0.450 27 4.50 0.00045 r 0.450 3.2 4.50 0.00045 r 0.450 3.6 4.50 0.00045 r 0.450 41 4.50 0.00045 r 0.450 4.5 4.50 0.00045 r 0.450 5.0 4.50 0.00045 r 0.450 5.4 4.50 0.00045 r 0.450 5.9 4.50 0.00045 r 0.450 63 4.50 0.00045 r 0.450 6.8 4.50 0.00045 r 0.450 7.2 4.50 0.00045 r 0.450 77 4.50 0.00045 r 0.450 8.1 4.50 0.00045 r 0.450 8.6 4.50 0.00045 r 0.450 9.0 4.50 0.00045 r 0.450 9.5 4.50 0.00045 r 0.450 9.9 4.50 0.00045 r 0.450 10.4 4.50 0.00045 r 0.450 10.8 4.50 0.00045 r 0.450 11.3 4.50 0.00045 r 0.450 11.7 4.50 0.00045 r 0.450 12.2 4.50 0.00045 r 0.450 12.6 4.50 0.00045 r 0.450 13.1 4.50 0.00045 r 0.450 13.5 SITE BASED STORMWATER MANAGEMENT PLAN — Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 33
APPENDIX D –STORMWATER CATCHMENT PLANS Pre-Development Site Catchment Post-Development Site Catchment SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
Page 34
S
E1
S
S
S
S
S
S
E1
S
S
S
E
E
E
S
S
S
S
S
E
E
E
S
18/09/2023 N:\M3024\STORMWATER MANAGEMENT\REV B\ACAD\M3024E_DA1_SK01
S
S
BRISBANE - SUNSHINE COAST - CENTRAL QLD PLANNERS PRE-DEVELOPMENT SITE CATCHMENT
BRISBANE URBAN DESIGNERS JOB NO: PLAN: ISSUE:
JFP House - 76 Ernest Street, SURVEYORS M3024E_DA1 SK01 B N
South Brisbane Qld 4101
P 07 3012 0100 W www.jfp.com.au ENGINEERS 36 & 38 DUKE STREET, SUNSHINE BEACH SCALE:
DATE:
1:100 @ A1
18/09/2023
JFP URBAN CONSULTANTS PTY. LTD. A.C.N. 050 414 045 LANDSCAPE ARCHITECTS
COPYRIGHT © 2011 JFP URBAN CONSULTANTS PTY LTD THIS DOCUMENT MAY NOT BE COPIED OR TRANSMITTED IN ANY FORM OR BY ANY MEANS IN PART OR IN WHOLE WITHOUT THE WRITTEN CONSENT OF JFP URBAN CONSULTANTS PTY LTD.
CAMBOOYA PTY LTD DRAFTED BY:
FILE NAME:
CB
M3024E_DA1_SK01.DWG
Page 35
D1
D2
RW RW
RW
S
RW
D1 RW
RW
RW
D3
18/09/2023 N:\M3024\STORMWATER MANAGEMENT\REV B\ACAD\M3024E_DA1_SK02
BRISBANE - SUNSHINE COAST - CENTRAL QLD PLANNERS POST-DEVELOPMENT SITE CATCHMENT
BRISBANE URBAN DESIGNERS JOB NO: PLAN: ISSUE:
JFP House - 76 Ernest Street, SURVEYORS M3024E_DA1 SK02 B N
South Brisbane Qld 4101
P 07 3012 0100 W www.jfp.com.au ENGINEERS 36 & 38 DUKE STREET, SUNSHINE BEACH SCALE:
DATE:
1:100 @ A1
18/09/2023
JFP URBAN CONSULTANTS PTY. LTD. A.C.N. 050 414 045 LANDSCAPE ARCHITECTS
COPYRIGHT © 2011 JFP URBAN CONSULTANTS PTY LTD THIS DOCUMENT MAY NOT BE COPIED OR TRANSMITTED IN ANY FORM OR BY ANY MEANS IN PART OR IN WHOLE WITHOUT THE WRITTEN CONSENT OF JFP URBAN CONSULTANTS PTY LTD.
CAMBOOYA PTY LTD DRAFTED BY:
FILE NAME:
CB
M3024E_DA1_SK02.DWG
Used in these records
Attachment F_Stormwater_Management_Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.