4     CONSOLIDATED ASSESSMENT MANAGER CONDITIONS

Land Use
1.    Development undertaken in accordance with this approval must generally comply with
      the approved plans of development. The approved plans are numbered A-WD-1-03 Rev
      A, A-WD-1-02 Rev A, A-WD-1-01 Rev B and A-WD-1-04 Rev B prepared by Casa
      Concepts and dated 01 Sept 01 and as may be amended by these conditions.
2.    The development must be undertaken and operated in a manner that causes no
      detrimental effect upon the amenity of the neighbourhood by reason of the creation of
      excessive noise, lighting nuisance or other emissions.
3.    Existing trees on the site and within road reserves are to be retained, except where
      required to be removed due to building operations or the conduct of the approved use.
4.    This Development Permit for a material change of use of premises lapses if:-
      4.1. the use or erection of a building or other structure associated with the use, has not
           been commenced by 3 February 2007, unless application is made and approved
           by Council for an extension; or
      4.2. the use of any premises pursuant to the Development Permit ceases.

Land Development
5.    All stormwater drainage shall be collected on site and discharged to the existing
      drainage structures leading to the absorption pit in the north east corner of the lot.
6.    All site stormwater drainage shall be by means of a gravity system.
7.    The recommendations of the report prepared by Golder & Associates dated May 2002
      as submitted by Bark Design shall be complied with in full.
8.    If any excavation work are require at or near any of the boundaries for the purpose of
      footing and foundation construction, care must be taken to ensure no earthworks/batters
      extend over the property boundary.
9.    To protect the environment against siltation/sediment export or soil erosion as a result of
      this development, an erosion and sediment control plan shall be submitted in
      conjunction with any Development Permit for Building Works. Site control measures
      such as silt fencing, controlled gravel access to the site and controlled disposal of waste,
      may be necessary. Prior to commencement of building works, all physical site control
      measures shall be installed, and the plan adhered to.
10.   Any damage caused to any public utility during the course of construction shall be
      repaired to Council’s standards and at no cost to Council.
11.   Any alteration of any public utility or other facilities necessitated by the development of
      the land or associated construction works external to the site shall be at no cost to
      Council.
12.   The transportation of all materials to and from the site shall be undertaken in a manner
      such that no particle matter escapes onto a public road. All vehicles carrying materials
      either to or from the site shall be covered to prevent materials including dust being
      windblown from the vehicle.
13.   To protect the environment against siltation/sediment export or soil erosion as a result of
      this development, site control measures such as silt fencing, controlled gravel access to
      the site and controlled disposal of waste, may be necessary. Prior to commencement of
      building works, all physical site control measures should be installed.




                                                                                    Page 2 of 6
Log in to download the original file

6119 - Att B - Current Approval - 132002.220527.1 (23069 DA).pdf · 4.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.