6119 - Att B - Current Approval - 132002.220527.1 (23069 DA)
132002.220527.1
4 CONSOLIDATED ASSESSMENT MANAGER CONDITIONS
Land Use
1. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are numbered A-WD-1-03 Rev
A, A-WD-1-02 Rev A, A-WD-1-01 Rev B and A-WD-1-04 Rev B prepared by Casa
Concepts and dated 01 Sept 01 and as may be amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no
detrimental effect upon the amenity of the neighbourhood by reason of the creation of
excessive noise, lighting nuisance or other emissions.
3. Existing trees on the site and within road reserves are to be retained, except where
required to be removed due to building operations or the conduct of the approved use.
4. This Development Permit for a material change of use of premises lapses if:-
4.1. the use or erection of a building or other structure associated with the use, has not
been commenced by 3 February 2007, unless application is made and approved
by Council for an extension; or
4.2. the use of any premises pursuant to the Development Permit ceases.
Land Development
5. All stormwater drainage shall be collected on site and discharged to the existing
drainage structures leading to the absorption pit in the north east corner of the lot.
6. All site stormwater drainage shall be by means of a gravity system.
7. The recommendations of the report prepared by Golder & Associates dated May 2002
as submitted by Bark Design shall be complied with in full.
8. If any excavation work are require at or near any of the boundaries for the purpose of
footing and foundation construction, care must be taken to ensure no earthworks/batters
extend over the property boundary.
9. To protect the environment against siltation/sediment export or soil erosion as a result of
this development, an erosion and sediment control plan shall be submitted in
conjunction with any Development Permit for Building Works. Site control measures
such as silt fencing, controlled gravel access to the site and controlled disposal of waste,
may be necessary. Prior to commencement of building works, all physical site control
measures shall be installed, and the plan adhered to.
10. Any damage caused to any public utility during the course of construction shall be
repaired to Council’s standards and at no cost to Council.
11. Any alteration of any public utility or other facilities necessitated by the development of
the land or associated construction works external to the site shall be at no cost to
Council.
12. The transportation of all materials to and from the site shall be undertaken in a manner
such that no particle matter escapes onto a public road. All vehicles carrying materials
either to or from the site shall be covered to prevent materials including dust being
windblown from the vehicle.
13. To protect the environment against siltation/sediment export or soil erosion as a result of
this development, site control measures such as silt fencing, controlled gravel access to
the site and controlled disposal of waste, may be necessary. Prior to commencement of
building works, all physical site control measures should be installed.
Page 2 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.