Attachment 15- Amended Water Supply and Sewerage Analysis MCU12/0208
Very large file (11.7 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Noosa on Weyba
Water Supply and Sewerage Analysis
6.5 Noosa Heads Sewerage Treatment Plant
Flow from the Noosa on Weyba development is proposed to be conveyed and treated at the Noosa Sewage
Treatment Plant (STP). Based on advice from Unitywater officers and publically available documentation,
preliminary investigations have indicated that the Noosa STP is at capacity. Augmentation to rectify the
capacity issues at the Noosa STP has been identified by the former Noosa Shire Council and has been
included in past Council budget minutes dating from 2008. Current advice from Unitywater has indicated that
the augmentation of the Noosa STP would be subject to review in 2012.
Analysis of the Noosa STP was detailed in a paper presented at the 2010 AWA Conference entitled, ‘So Tell
Me Again, Why Do I Need To Upgrade An STP With 225 Ml/D Capacity When It’s Only Treating 150 Ml/D?,
M.Thomas, Unitywater. This paper highlighted that the capacity at the Noosa STP is primarily related to the
influent Biological Oxygen Demand (BOD) and COD (Chemical Oxygen Demand). COD and BOD represent
the relative strength of the influent sewage with levels of governing downstream treatment processes. This
could include the capacity of the bioreactors and clarifiers as well as the sludge processing stream. Table 6-7
below from the AWA conference paper compares the design capacity of the Noosa STP to the actual current
plant loadings.
Table 6-7 Noosa STP Design Capacity and Current Plant Loadings
Current Loading (EP)
Design
Capacity Total
(EP) 2009/10 Total
COD BOD Suspended Total Phosphorous
Hydraulic Nitrogen
Solids
48,000 40,000 61,538 69,231 62,500 42,000 44,444
The table highlights that while the plant appears to be capable of treating the current hydraulic, Nitrogen and
Phosphorus loads, the current design capacity is not suitable to treat the BOD/COD and Suspended Solids
loads.
Advice was sought from Unitywater regarding capacities and the potential for augmentation at the Noosa
STP. Unitywater, via Ashley Lorenz, provided the following advice:
Noosa Sewage Treatment Plant has capacity to serve existing sewer connections and new
development designated in the current Noosa planning Scheme until late 2015. This assessment is
based upon Unitywater’s assessment of the performance of the plant and certain assumptions
about; rate of growth, influent characteristics and approval of new development not extending
beyond the urban area detailed in the Noosa Planning Scheme as at June 2012.
The Noosa Sewage Treatment Plant is operating beyond certain aspects of its design capacity but is
producing effluent which complies with that prescribed in the environmental licence.
Unitywater is satisfied that the Noosa Sewage Treatment Plant is being operated very efficiently.
Unitywater and the treatment plant operator, Degrémont, have commenced preparation of a
business case for augmentation of the Noosa Sewage Treatment Plant. Based upon the outcomes
of an options analysis Unitywater’s Board has approved, in September 2012, a revised strategy for
augmentation of the Noosa Sewage Treatment Plant which includes a delay in the preparation of the
business case until such time as Unitywater obtains a new environmental licence. Unitywater will
lodge a development application for augmentation of the treatment plant in January 2013 and is
targeting a decision notice being issued in June 2013. It is expected that the augmentation will be
commissioned in December 2015.
The full letter from Unitywater is detailed in Appendix D. In addition, confirmation has been sought from
Unitywater in regard to the upgrade of the Noosa STP. Unitywater have acknowledged and are considering
the treatment solutions to support the proposed development. Moreover, they have invited submission and
dialogue for the proposed development to be supported by future STP augmentation. All correspondence
with Unitywater has been provided in Appendix G
Northbrook Corporation Pty. Ltd. Version 4 17 September 2013
5101-19 Commercial in Confidence Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 15- Amended Water Supply and Sewerage Analysis MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.