Decision Notice
Attached to the e-mail Applicant Request for Amended Decision Notice to update approved plan of subdivision & feedback regarding IC Notice - MCU15 0095 & REC15 0022.
Noosa Council documents
MCU15/0095
Aboriginal Cultural Heritage Act 2003
2. There may be a requirement to establish a Cultural Heritage Management Plan
and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH
Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A
person who carries out an activity must take all reasonable and practicable measures
to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to
fail to comply with the duty of care. Substantial monetary penalties may apply to
individuals or corporations breaching this duty of care. Injunctions may also be
issued by the Land and Resources Tribunal, and the Minister administering the ACH
Act can also issue stop orders for an activity that is harming or is likely to harm
Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural
heritage.
You should contact the Cultural Heritage Unit on ph.07 32476212 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not Applicable
9 PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME
Not Applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
The following further development permit is required:
Development Permit for Operational Works (Stormwater Management)
11 SELF ASSESSABLE CODES
Not Applicable
12 SUBMISSIONS
361 Properly Made Submissions were received.
13 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions
from the Sustainable Planning Act 2009 is attached.
During the appeal period, you as the applicant may suspend your appeal period and
make written representations to Council about the conditions contained within the
development approval. If Council agrees or agrees in part with the representations, a
“negotiated decision notice” will be issued. Only one “negotiated decision notice” may be
given. Taking this step will defer your appeal period, which will commence again from
the start the day after you receive a “negotiated decision notice”. (Refer to Part 8
“Dealing with decision notices and approvals” - Division 1 “Changing decision notices
and approvals during applicant’s appeal period” of the Sustainable Planning Act 2009.)
Page 4 of 21
Document Set ID: 20060077
Version: 1, Version Date: 29/04/2016 Print Date: 29 April 2016, 4:34 PM