Decision Notice - Approved by Delegation of Authority MCU26 0001 - AS PUBLISHED · MCU26/0001
28. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Easements
29. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
30. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
31. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Geotechnical Stability
32. All works must be carried out in accordance with the recommendations contained in
Tectonic’s Geotechnical Investigation (25408-001-Rev0) dated 30 January 2026 listed within
this Decision Notice.
Earthworks and Retaining Walls
33. All earthworks and associated retaining structures/batters, both above and below ground,
both temporary and permanent, must be undertaken in accordance with the conditions of this
Decision Notice, be generally in accordance with the conditions of this Decision Notice and
be generally in accordance with Barlow Shelley’s Bulk Earthworks Plan (C101, Rev. A) dated
15 May 2026 and contained entirely within the subject site unless written permission from
the respective landowner(s) is provided to Council.
Damage to Services and Assets
34. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Demolition of Relevant Structures
Codes of Development
35. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan 2020.
Works
36. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste Management
37. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
Page 6 of 19
Document Set ID: 25157850
Version: 2, Version Date: 10/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority MCU26 0001 - AS PUBLISHEDRelated documentApplication case desk ↗
About this file
- File size
- 200 KB (small file)
- File type
No other editions are linked here.