c. Ensure clearing works avoids nesting times of animals and birds.
d. Provide a written report to Council with the request for the prestart meeting of all pre-
clearing activities and initiatives.
e. Co-ordinate staging and sequence of clearing with fauna protection.
f. Protect and recover fauna during clearing operations (fauna not previously removed).
g. Manage the translocation of animals and recovery procedures in accordance with
relevant legislation.
h. Undertake protection works for mulching of any stockpiled vegetation.
i. Provide certification to Council prior to the issue of building approval, the works were
conducted in accordance with the approved Fauna Management Plan.
*(Refer to Advisory Note)
Removal of Existing Trees and Vegetation
50. Vegetation removal, felling and lopping must:
a. Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
b. Mulch all other wood and leaf material (without root balls, soil or debris and minimising
weed seeds) for re-usable mulch.
c. Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
of three months.
d. Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
between piles*.
e. Allow for existing endemic ground flora to be translocated to suitable landscaping and
rehabilitation areas.
f. Conclude with the area being stabilised against erosion, landscaped, rehabilitated and
revegetated.
*(Refer to Advisory Note)
Landscaping Works
51. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice, prior to the
commencement of use for each stage.
(* Refer to Advisory Note)
52. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
53. Landscape works must:
a. Ensure compliance with the approved Landscape Plans, as amended by Council.
b. Ensure native trees of a minimum bag size of 100L are established to replace existing
trees to be removed from the site, at the rate of 1 replacement tree for every tree
removed that has a diameter greater than 200mm measured at 1.2 metres from ground
surface level.
c. Ensure amenity or sales signage and ancillary infrastructure is not installed within the
road reserve.
d. Ensure permanent irrigation is not installed within the road reserve.
e. Ensure works are in accordance with the approved bushfire report.
Page 12 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval OPW19 0266 03.pdfRelated documentApplication case desk ↗
About this file
- File size
- 245 KB (small file)
- File type
No other editions are linked here.