23176DA Change a Decision Notice [As Published] · 132003.220653.3
2003/220653
Town Water Supply
104. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
105. Each water connection to the water reticulation system shall extend to the property boundary
and be metered. Where multiple units are served by a single service, multiple water meters to
each individual unit and for the body corporate shall be installed. All fees for the supply of
water meters shall be paid to the Council.
Service Easements
106. All existing and proposed easements within the site shall be shown on the plans submitted for
Operational Works / Building Works approval.
107. Registered easements shall be created over any Council service within the subject site in
accordance with Council’s requirements (if not already created) and at no cost to Council.
The Applicant’s Solicitor shall give Council’s Solicitor an appropriate undertaking in writing that
the Title Deed and the easement documents will be lodged at the Land Titles Office and any
additional Titles Office forms or requisitions requiring the consent of Council will be attended to
promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the
use commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
Earthworks
108. Plans and details outlining the extent of earthworks required on site and any trees to be
retained shall be submitted to Council for approval prior to obtaining a Development Permit for
Operational Works.
109. All major excavations (including the basement and driveways) shall be shored to prevent
batters extending into areas and vegetation that are to be retained. All trees to be retained
should be adequately tagged to Council’s satisfaction and enclosed with a barrier fence to the
drip line to prevent damage.
110. A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures and/or land, and make recommendations on
the type of foundation system(s) best suited for the proposed development. The
recommendations of this report shall be incorporated into the design and construction of the
proposed development.
111. Earthworks shall not cause the ponding of water on any adjoining lands or the blockage of, or
interference with, any natural watercourses or overland flow path.
Erosion and Sediment Control
112. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site, controlled
disposal of waste, catch drains, and temporary infiltration or sump pump-outs will be
necessary.
Plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
The applicant is advised that a simple silt fence by itself is unlikely to meet the objectives of
best practice for Erosion & Sediment Control.
Page 16 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
23176DA Change a Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 111 KB (small file)
- File type
No other editions are linked here.