Engineering report 1 George St rev C · REC15/0011
Attached to the e-mail REC15/0011 - Information Response.
Proposed Subdivision
1 George Tewantin
thus the long term maintenance requirements for Council would effectively be
greater not less.
Our concept design therefore proposes bio retention basins to treat the stormwater
run-off from the site, however instead of one larger basin, two smaller basins have
been proposed to minimise impacts on existing trees and to make use of the natural
lay of the land. Following discussions with Council at the prelodgement meeting,
water from the lots is conveyed to the bio retention basins via a conventional piped
interlot drainage system. A gravel access originally proposed down the eastern
and western side of the site to provide access for maintenance of the bio retention
basins has now been deleted as per Councils information request dated 4 August
2015.
In regard to run off from the existing road and footpath area of George Street,
Council has now indicated a desire replace the existing flush kerb with a
conventional kerb and channel, however the footpath levels shall generally remain
as they are. There is a large gum and a strand of melaleuca trees immediately
adjacent to the existing road pavement that will need to be removed to allow the
installation of the new kerb and channel, but following further discussions with
Council staff it is understood that this is desirable due to the potential for long term
damage to the road pavement. Water collected in the new kerb and channel will be
collected in new gully pits at each end for the development site and conveyed by a
conventional pipe system to the proposed outlets.
The gully pit at the eastern end will drain to the proposed bio retention basin behind
lot 2 within the drainage/environmental reserve, however the outlet for the western
end will be directed into the Council reserve and ultimately to Wooroi Creek to
minimise impacts on exiting trees in the environmental/drainage reserve caused by
further pipe drainage installation. It should be noted that this pit is only collecting
water from the existing George Street road pavement area that already flows into
Wooroi Creek without any quality treatment. This has been depicted on the revised
concept plans.
4. CONCEPT DESIGN FOR WATER AND SEWER
In regard to the sewer service we are able to command all of the new lots using a
gravity sewer system connecting to an existing sewer manhole in George St. To
avoid trenching adjacent significant trees along the frontage on George St we have
elected to take the sewer down the side boundary of lot 1 (in the balance lot) on an
alignment that avoids any existing significant trees. The manhole at the north east
J/N 15513 October 2015
Rev C Page 2 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Engineering report 1 George St rev C.pdfRelated documentApplication case desk ↗
About this file
- File size
- 311 KB (small file)
- File type
No other editions are linked here.