EXECUTIVE SUMMARY
ADG Engineers (Aust.) Pty Ltd has been engaged by Aspect Architects to prepare a Site Based
Stormwater Management Plan (SBSMP) suitable for submission to Noosa Shire Council (NSC) as
additional information in support of a Development Application for a Material Change of Use for a
proposed Eco Resort Extension to the current RACV Noosa Resort located at 94-142 Noosa Drive,
Noosa Heads QLD 4567.
The proposed development as shown in Aspect Architects plans issued on 30.06.2023 is for eight
(8) double storey eco resort style units, raised boardwalk footpath links and associated carparking.
The proposed application to Council also includes works involving converting an existing pond
internal to the RACV Noosa Resort site into a new pool. ADG make note that this existing pond does
not form part of an existing site-based stormwater treatment train nor provides further stormwater
detention management. The pool works is to form part of separate application submitted to Council
for building approval.
The report comprises of stormwater quantity and quality assessments. The quantity assessment is
undertaken to confirm a ‘non-worsening’ of peak flow discharges from the site and the quality
assessment is undertaken to determine the required stormwater treatment measures to be
implemented on site.
The stormwater quantity objective was to demonstrate that there are no impacts from storm events
up to and including the 1% AEP storm event. The purpose is to ensure that the existing infrastructure
and/or downstream properties are not adversely affected. Due to negligible increase in peak flows
from the subject site and the subject site being located close to the downstream waterway hence in
the lower portion of the regional catchment, it is considered unnecessary to include provision for
stormwater quantity management as the proposed runoff is intended to infiltrate into the existing sub-
surface utilising bio infiltration basin. The In-situ Constant Head Permeability Test using the Talsma-
Hallam Test method (per AS1547) undertaken by Tectonics Geotechnical & Environmental
Engineers has confirmed the hydraulic conductivity of the soil is capable to infiltrate the retained
water with an exfiltration rate of 115 mm/hr.
Currently no stormwater quality management measures are in place for the Eco Village subject site.
Stormwater treatment measures are proposed to be implemented on site in accordance with Industry
Best Practice, WSUD Engineering Guidelines and, Council’s Land Development Guidelines to
provide stormwater treatment for this site. ADG recommends the use of the following devices to meet
the water quality objectives identified within the SPP 2017 and Council’s WSUD Planning Scheme
Policies:
Combined 40kL Rainwater Tank (Reuse) and downpipes to convey the overflow to the bio
infiltration basin area.
60m2 bio infiltration basin that will permit flows to infiltrate into the subject sites sub-surface.
The eMUSIC model compares the pre and post-development stormwater pollutant residual loads in
Section 6.6 of this report. ADG advise the post-development pollutant residual loads are now below
the pre-development stormwater pollutant residual loads and that water is intended to infiltrate into
the sub-surface strata of the subject site through the drainage layer of the proposed bio infiltration
basin. This results in no increase in gross pollutants, total suspended solids, total phosphorus, nor
total nitrogen compared to the pre-development scenario.
To address the Noosa Shire Council’s RFI dated 6th April 2023, the following has been added to this
SBSMP:
The originally proposed 30m2 bio infiltration basin area is upsized into 60m2 surface and filter
area. Refer to Appendix C of this report for updated plans with bio basin details.
BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdfRelated documentApplication case desk ↗
About this file
- File size
- 35.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.