RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads
ADG Ref: 22366 C R10 Rev07 21.07.2023.docx
July 2023
An In-situ Constant Head Permeability Test using the Talsma-Hallam Test method (per AS1547)
was undertaken by Tectonics Geotechnical & Environmental Engineers and confirmed that the
site has 0.6m sand clay topped over silty sand which is up to 1.7m deep. Saturated soil
permeability (Ksat) was assessed from the results and confirmed the rapid infiltration at the test
location with an ex-filtration rate at 115mm/hr. There are no ground water investigated at the
boreholes during the tests.
The in-situ saturated hydraulic conductivity results have been updated in the MUSIC model to
reflect the In-Situ Constant Head Permeability Test results. Refer Appendix H of this report for
updated MUSIC model details.
The overflow from rainwater tanks are proposed to be conveyed using down pipes and discharge
into bio basin area through localised 200mm deep vegetated swales, where the natural
topography falls away from the discharge point. The runoff from raised timber walkway will fall
directly to the natural surface below, which as demonstrated has adequate exfiltration properties.
In the post-developed MUSIC model, the timber walkway node is modelled using the parameters
for existing vegetated surface as agreed by NSC Assessment Officer (Leon Rowland from
Switchback Consulting on behalf of NSC). Further, it is not considered practical to capture water
run-off from a raised timber walkway structure. The bio infiltration basin has been oversized to
compensate for the water quality catchment area of the walkway structure.
All relevant standards and guidelines are addressed in this Stormwater Management Plan
including criteria from the Noosa Shire Council Planning Scheme Policies, Queensland Urban
Drainage Manual (QUDM) 2016, State Planning Policy (SPP) 2017 Plumbing and Drainage Code
AS3500.3 and Australian Rainfall and Runoff Guideline (ARR).
BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA Page 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdfRelated documentApplication case desk ↗
About this file
- File size
- 35.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.