2ND RFI - Attachment 4A - Stormwater Management Plan (2) · MCU22/0118

of 82

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (35.2 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                        ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023

            An In-situ Constant Head Permeability Test using the Talsma-Hallam Test method (per AS1547)
            was undertaken by Tectonics Geotechnical & Environmental Engineers and confirmed that the
            site has 0.6m sand clay topped over silty sand which is up to 1.7m deep. Saturated soil
            permeability (Ksat) was assessed from the results and confirmed the rapid infiltration at the test
            location with an ex-filtration rate at 115mm/hr. There are no ground water investigated at the
            boreholes during the tests.

            The in-situ saturated hydraulic conductivity results have been updated in the MUSIC model to
            reflect the In-Situ Constant Head Permeability Test results. Refer Appendix H of this report for
            updated MUSIC model details.

            The overflow from rainwater tanks are proposed to be conveyed using down pipes and discharge
            into bio basin area through localised 200mm deep vegetated swales, where the natural
            topography falls away from the discharge point. The runoff from raised timber walkway will fall
            directly to the natural surface below, which as demonstrated has adequate exfiltration properties.
            In the post-developed MUSIC model, the timber walkway node is modelled using the parameters
            for existing vegetated surface as agreed by NSC Assessment Officer (Leon Rowland from
            Switchback Consulting on behalf of NSC). Further, it is not considered practical to capture water
            run-off from a raised timber walkway structure. The bio infiltration basin has been oversized to
            compensate for the water quality catchment area of the walkway structure.

            All relevant standards and guidelines are addressed in this Stormwater Management Plan
            including criteria from the Noosa Shire Council Planning Scheme Policies, Queensland Urban
            Drainage Manual (QUDM) 2016, State Planning Policy (SPP) 2017 Plumbing and Drainage Code
            AS3500.3 and Australian Rainfall and Runoff Guideline (ARR).




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA          Page 6

Used in these records

About this file

File size
35.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdf · 35.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.