Appeal judgement 30-32 Doonella St Tewantin - MCU21-0013 OPW21-0013
Original PDF page 17, section 1. The text section number identifies this passage in the reader.
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in
the projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
99. Council may request further controls to be installed should the implemented measures
be found inefficient.
100. The erosion and sediment control measures must be designed, installed and maintained
in accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
101. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and
prior to rainfall occurring.
102. The developer in conjunction with the engaged CPESC must ensure measures installed
to divert the upstream water are designed and certified by the supervising RPEQ and
installed prior to commencement of bulk earthworks.
103. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles
and/or machinery. It is essential to implement appropriate approved erosion and
sediment control measures throughout the site during all phases of construction
including vehicle shakedown pad/grid (or similar) at the access to the construction site.
Where sediments or other contaminants are deposited on a road, they must be removed
so as not to enter Council’s drainage system or waterways.
104. Prior to the completion of the development, all site surfaces must be effectively
stabilised. For the purpose of this condition, an effectively stabilised surface is defined
as one that does not, or is not likely to result in visible evidence of soil loss caused by
sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Water Sensitive Design
105. The active filter media of the bioretention device must be 27m². Active filter media area
is the area of the bioretention basin surface that is not covered by any impermeable
structure such as a sediment forebay, riser, etc.
106. During construction and establishment of the bioretention devices, the supervising
RPEQ must certify forms contained in section 3.15 of the Construction and
Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
Design, 2009). These forms and certification must be submitted to council prior to the
sealing of the survey plan.
107. A construction hold point with a council delegate must be established once the
bioretention device underdrainage pipe work is installed. At the time of inspection, a
sample of the drainage layer, transition layer, and filtration media materials must be
stockpiled onsite accompanied by laboratory results that demonstrate that the media
complies with the specifications contained in the latest version of the Guidelines for Soil
Filter Media in Bioretention Systems (Facility for Advancing Water Biofiltration) and that
the minimum hydraulic conductivity of 180mm/hr or as specified on the approved
engineering plans will be achieved. The drainage layer, transition layer, and filtration
media materials shall not be installed until the catchment draining to the bioretention
device has 80% groundcover as determined by council’s delegate.
108. Eighty percent (80%) of the catchment flowing to the bioretention basin must be
effectively stabilised prior to the construction holdpoint for the Bioretention device.
15