Appeal judgement 30-32 Doonella St Tewantin - MCU21-0013 OPW21-0013
Original PDF page 18, section 1. The text section number identifies this passage in the reader.
109. Prior to the release of the plan of survey, the supervising RPEQ must certify must certify
that all hardstand areas of the development drain to a bioretention device designed and
constructed in accordance with all relevant conditions of this approval, the Water by
Design Bioretention Technical Design Guidelines, relevant aspects of the IPWEAQ
Standard Drawing WSUD-drawing series and Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands (Water by Design, 2009).
Bioretention Devices - Landscaping
110. Landscape plans must include a mixture of at least five of the following species for
planting in the bioretention basin extended detention surface at a minimum density of 8
plants/m2:
e. Carex appressa
f. Carex fascicularis
g. Ficinia nodosa
h. Juncus usitatis
i. Lomandra longifolia
j. Ghania sieberiana
111. Landscape plans for the areas surrounding the bioretention basin filter media footprint
must be arranged to minimise shading to the filter media footprint are. Suitable plants
include the following:
k. Carex appressa
l. Carex fascicularis
m. Ficinia nodosa
n. Juncus usitatis
o. Lomandra longifolia
p. Ghania sieberiana
q. Banksia robur
r. Dianella brevipendunculata
s. Themada triandra
t. Cymbopogan refractus
u. Melaleuca thymifolia
112. Where landscaping/garden beds are proposed adjacent to the bioretention basin, or
where the basin is located adjacent to naturally forested areas, a 900mm deep root
barrier must be installed to the interface between the landscape/garden/forest area and
the bioretention basin to prevent root intrusion to the biobasin infrastructure.
113. Landscaping to the surface of the bioretention basin filter media area must not
commence until 80% of building work within each contributing catchment is complete or
after 3 years, whichever occurs first. An uncompleted works bond of 150% of the value
of the planting to the surface of the bioretention basin filter media area must be provided
to Council prior to the release of the Plan of Survey.
114. Where required, mulch within the batters of bioretention basins must be installed in a
manner that it will not escape into receiving stormwater drainage infrastructure or water
courses.