Capital Program 2024/2025 Delivery Status · Report

of 8

Text shows just the words. Original shows the document exactly as it was published.

SERVICES & ORGANISATION COMMITTEE MEETING                                        12 AUGUST 2025


•   Tewantin, Sheild Street/Werin Street
•   Tewantin, Waratah Close
•   Tewantin, Yellowwood Drive/McKinnon Drive
Noosa Biosphere Trails
Upgrade works on the Noosa Biosphere Trails have continued through Q4 of 2024/25. Works are
still ongoing on:
•   Twin Hills, Wahpunga Trail – disaster landslip works (Expected completion Q2 2024/25)
•   Cooran to Kin Kin, Woondum Trail (Trail 3)
•   Kin Kin to Lake Macdonald Wahpunga Trail (Trail 4) - Renewal
Planning is ongoing on the following trails:
•   Boreen Point to Tewantin, Cooroibah Trail
•   Lake McDonald to Peregian Beach, New Weyba Trail
•   Pomona to Cooroy, Kurui Trail – Renewal
See Attachment 1 for photos of completed trails works completed during Q4.

Planning and Design
The Infrastructure Planning team had a busy quarter with preparation for the 2025/26 financial year
Capital Works Program and Council endorsement of the Noosaville Foreshore Infrastructure
Masterplan being the key focus.
In addition to the above, the Planning and Design teams are currently managing over 25 Capital
projects and have provided planning and design services to over 60 projects in the 2024/25 financial
year.

The following projects have been in various stages of planning and design during Q4:
•   Local Government Infrastructure Plan update – Progressing with strategic planning coordination
•   Noosaville Foreshore Master Plan – Council endorsement received with planning works ongoing
•   Noosa Heads, Noosa Woods Jetty Upgrade Investigation
•   Noosa Heads, Main Beach Seawall Design
•   Noosa, Noosa Drive Footpath and Boardwalk – Preliminary Design Completed
•   Noosaville, Noosaville Foreshore Changing Places
•   Noosaville, Weyba Reef Roundabout Design – Concept Design Completed
•   Peregian Beach, Coastal Pathway Stage 1
•   Cooyar St Bio-basin
•   Landscape Infrastructure Manual
•   Gympie Terrace Revetment Wall Grant Application
•   Noosa Entry Signage Guidelines
•   Hilton Esplanade Active St, Stormwater and Living Foreshore Upgrades
•   Shire Wide, Bus Stop Program – Design nearing completion on the final bus stop in the 10-year
    PTAIP program
•   Shire Wide, Pathway Program
•   Various trail projects

Used in these records

About this file

File size
278 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Report.pdf · 278 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.