Construction and establishment of stormwater management systems Table 9.4.8.3 Criteria for assessment (part)
Performance Outcomes Acceptable Outcomes Response
Construction and establishment of stormwater management
systems
PO14 AO14.1
Construction methods provide for appropriate controls to avoid An erosion and sediment control plan prepared in accordance The proposed driveway is to be placed at the location of the
with the International Erosion Control Association Best Practice existing driveway for the allotment and best practice
entry and transport of litter, sediment, and associated
Books demonstrates that the capture and release of stormwater construction methods for civil works will be implemented.
prescribed water contaminants into receiving waters.
achieves the design objectives listed in Table A: Construction PO14 and acceptable outcomes AO14.1, AO14.2, AO14.3
phase – stormwater management design objectives of the State can be achieved.
Editor's note— Water contaminants are prescribed in the
Planning Policy (Appendix 2).
Environmental Protection Act 1994.
Editor’s note— PSP6 Engineering Design Standards - Roads,
drainage and earthworks provides guidance on requirements for
preparing an Erosion Management Plan.
AO14.2
Construction works are designed and managed to restrict the
extent of clearing and soil exposure to the minimum necessary for
access, and safe construction at any one time.
AO14.3
For buildings:
(a) upstream runoff is diverted around the construction site;
(b) sediment barriers are provided downslope of disturbed
areas to prevent sediment washing into gutters, drains and
waterways , wetlands or drainage lines either on or off the
site; and
(c) temporary or permanent downpipes are connected to the
stormwater system before laying the roof; or
(d) localised erosion is avoided by directing flow from
downpipes over non-erosive areas.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.