OPW052025 Report - Part 2
Attached to the e-mail Operational Works Application OPW25/0093 - OPW Report Part 2 _May 2025 - 146 Middle Creek Road_ Federal - Email 2 of 2.
Very large file (17.0 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Approx. house site on
crest of knob
Actual driveway route to
be adopted
Middle Creek Road
Text Figure 1: Sketch of proposed works (provided by SQ)
3. Aims & Method of Investigation
The main aims of the investigation were to address landslide risk and to provide guidance regarding
geotechnical matters for the proposed driveway and residential building. The investigation and report
have been designed to address the requirements of the relevant Noosa Council (NC) codes and policies
regarding slope stability.
3.1 Fieldwork
An experienced engineering geologist from Tectonic undertook an initial site walk-over on 13 March
2025 to visually assess any indicators of past slope instability. The walk-over included assessment of soil
and rock exposures, surface drainage conditions, topography, evidence of erosion, existing structures
and vegetation coverage/condition (as detailed in Section 4 below).
Five test pits were undertaken using a 5.5 tonne excavator with toothed bucket and ripper attachments
to depths of between 0.9 m and 3.2 m below ground level (BGL). One scrape was also completed on the
cut batter where the driveway is sidelong across the slope.
Geotechnical Investigation & Slope Stability Assessment
9 April 2025 | 25050-001-Rev0 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.