RFI - Attachment B - Stormwater management Report · MCU20/0026
Original PDF page 8, section 1. The text section number identifies this passage in the reader.
Table 2 - Catchment Summary
Model Event Catchment Roof Catchment Slope %
Area (Ha) Excluded (Ha) (%) Impervious
Pre-Developed 10% AEP 0.037 0.018 24 16
1% AEP 0.043 0.012 24 30
Post-Developed 10% AEP 0.028 0.027 24 34
1% AEP 0.037 0.018 24 49
3. 2 X P St or m Re su lt s
The results of the ensemble statistics utility are presented in Figure 2 & Figure 3 below.
Figure 2 - Ensemble Statistics Utility Results; 10% AEP
Figure 3 - Ensemble Statistics Utility Results; 1% AEP
11 June 2020 Stormwater Management Report 5
S20-023 40 Park Crescent, Sunrise Beach
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - Attachment B - Stormwater management Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.