Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                    RA-TGS PREPARATION                                           HIERARCHY OF CONTROL
                 Project Coordinator completes TGS in           To properly manage exposure to foreseeable risks a person on
              accordance with Aaction Traffic and DTMR          location, consider the appropriateness of control measures in the
            (MUTCD) standards and client requests (OPS-         following descending order of effectiveness:
                               FORM-008)                           • Elimination: Elimination the hazard entirely
                                    ↓                              • Substitution: If not possible to remove, minimise the risk
             Project Coordinator prepares RA-TGS as per                by substitution of a lesser risk.
                                drawings                           • Isolation: Isolating the hazard giving rise to the risk
                                    ↓                              • Engineering: Minimise the risk by engineering means
              Identify risks/impacts associated with each          • Administration: Applying administrative measures
                               activity step                       • Personal: Protective Equipment: Wear appropriate PPE
                                    ↓                                  at the worksite
           Assess consequences and likelihood of each risk
                                    ↓                           This Risk Assessment has been prepared as per the
                            Assess level of risk
                                    ↓                           Manual Of Uniform Traffic Control Devices Part 3, Eighth
             Determine appropriate control measures to          Issue, ( July 2018), Clause 2.2.3.b – A Risk Assessment is
                eliminate the risk or reduce it to as low       appropriate, “When preparing traffic guidance schemes
             reasonably practicable (refer to Hierarchy of      for more extensive or complex works where site specific
                                 Control)
                                    ↓
                                                                risks will assume importance. “
           Project Coordinator in charge of RA-TGS to sign
                               Cover Page
                                    ↓
            All Stakeholders to monitor activity and make
             suggestions for improvement to the RA-TGS




Issued:                                       Traffic Guidance Scheme & Scope of Works                  Uncontrolled when printed
Revised:          Version 1          Author: Shaylene Rubach        Approved by: Wayne Grice                    Page 8 of 9

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.