Skip to the record
Noosa's #1 Council Tracker.

Council archive · source document

Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                   mcnab construction
                                                                                    07-DOC-003 Rev 4

2     EMP application and authorisation
2.1             Client / project specific requirements
[EClientReq]

2.2             Application
This EMP is designed to achieve environmental best practices during the construction of Infinity
Apartments – Gympie Tce Noosaville and also meet the requirements of the Moreton Bay Regional
Council Development Approval.

2.3             EMP Authorisation
The Project Manager undertakes a risk assessment upon taking possession of the site. These
controls will be documented within the EMP by the Project Manager with assistance of the HSE
Team prior to mobilisation. All McNab project personnel are to ensure that their work activities and
those of consultants, subcontractors and suppliers are carried out in accordance with this EMP.

I, Steve O'Connor have reviewed this Environmental Management Plan and authorise its use for
Infinity Apartments – Gympie Tce Noosaville and hereby will implement all controls listed.

Name: Steve O'Connor Signature:                                   Date:

2.4             Distribution
This EMP is a Controlled Document.

The controlled document is stored electronically within the Job File. The printed copy should be
checked to see that the revision number is the same as the electronic version. The person in
possession of the physical copy is responsible for ensuring their copy is up to date. If in doubt,
please contact the Project Manager, or the HSEQ Manager.

2.5             Revision
The Project Manager will monitor the site and review the need for change or improvement to the
EMP in regard to:

      •     Senior Management Review
      •     Client comments, suggestions and special request
      •     Change in scope of work
      •     Project personnel suggestions and comments
      •     Necessity for corrective of preventative action, such as if an incident or near miss occurs
      •     Incidence and frequency of non-conformance
      •     Where latent conditions present themselves that weren’t considered during the site
            mobilisation (for example discovery of pests or historic artefacts).
      •     Results of internal audit, inspections or continual review
      •     Changes in legislation, standards or technology




Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan                                                                                       Page 7 of 39

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.