5.3 Monitoring
The responsibility for general environmental monitoring rest with all personnel engaged in the
project.
More specifically the HSE Team shall monitor each element of the construction process to ensure
that appropriate environmental controls are in place. The HSE Team shall undertake Compliance
Audit Inspections [06.44] and random site audits, and direct action as may be considered necessary
to protect, minimise or rectify any environmental concerns.
5.4 Consultation / Notification
McNab undertake to advise adjacent property owners / managers prior to the commencement of
the workers the following:
• Project description
• Actions contained in the EMP to protect environmental values
• Details working times
• Existence of a complaints procedure
• Contact details for complaints.
Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan Page 16 of 39
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.