Construction Management Plan
for Infinity Apartments
1.5 Project Duration
Anticipated Construction Commencement Date: December 2019
Anticipated Construction Completion Date: September 2020
1.6 Hours of Operation
Normal working hours for the project will be Monday to Saturday from 6.30am to 6.30pm in
accordance with the Development Approval.
If any works are to take place outside these hours, approvals will be obtained from the relevant
authority/s.
1.7 Community Consultation.
McNab are committed to open and clear consultation with the community. Prior to establishing site,
McNab will undertake a letterbox drop with a flyer containing key details of the project,
Commencement date and estimated completion date
Contact details for any queries and complaints (24hrs)
Details of all approval for the project
Details of all relevant parties – Developer, consultants etc
McNab will continue to letterbox drops through the life of the project to ensure the community is kept
aware of the projects evaluation including any changes to traffic management conditions.
05-DOC-001 Rev 0 - Construction Management Plan p5 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.