mcnab construction
Construction Management Plan
for Infinity Apartments
2. TRAFFIC MANAGEMENT
The management of traffic within the surrounding area will be undertaken in accordance with the
attached Traffic Management Plant (TMP) – Refer Appendix 1.
The Traffic Management Plan (TMP) describes how McNab proposes to manage the safe and orderly
passage of motorists, pedestrian traffic, emergency vehicles and other road users through and around
the site during the construction.
2.1 Local Haulage Routes
All vehicles will approach site from the west along Gympie Tce. Vehicles will enter site in forward
gear, unload materials and exit site in forward gear.
McNab will advise trucks and construction vehicles of the accepted entry and exit routes to the site.
Delivery routes will take into consideration of the traffic volumes and requirements of a safe and
effective flow of traffic within the area.
Construction vehicles are not to queue in any of the surrounding streets.
2.2 Temporary Vehicular Access
Vehicle access to site will be via Gympie Terrace. Vehicles will be able to enter and exit site in
forward gear. Where considered necessary or when demanded under the conditions of any permit,
accredited & Queensland transport licensed traffic controllers shall be used to direct traffic. All
traffic will be stopped or diverted in accordance with the methods set out in the Manual of Uniform
Traffic Control Devices (MUTCD).
2.3 Temporary Closures
During the course of construction there will be limited instances where McNab will be required to
partially close a road, footpath and/or car spaces to safely undertake the works. Where any road,
footpath or car space closures are required, approvals/permits must be obtained from the relevant
authority/s.
2.4 Loading/Unloading
Deliveries must be registered each day with the site team during the Pre-Start Meeting. The Site
Manager will ensure that impact on the local traffic is minimised. Unloading and loading will be
performed within the noted zones by the use of the crane, materials hoists, and forklift or by hand.
No unloading or loading will be permitted on the footpath without an approved Traffic Management
Plan in place and approved by the relevant authority/s. The frequency of deliveries shall be in line
with the construction programming. In order to limit deliveries, the Contract Administrator will
ensure a system of Just in Time ordering is implemented.
05-DOC-001 Rev 0 - Construction Management Plan p6 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.