Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                          mcnab construction
                                                                                Construction Management Plan
                                                                                         for Infinity Apartments
2.       TRAFFIC MANAGEMENT
The management of traffic within the surrounding area will be undertaken in accordance with the
attached Traffic Management Plant (TMP) – Refer Appendix 1.

The Traffic Management Plan (TMP) describes how McNab proposes to manage the safe and orderly
passage of motorists, pedestrian traffic, emergency vehicles and other road users through and around
the site during the construction.

2.1 Local Haulage Routes

     All vehicles will approach site from the west along Gympie Tce. Vehicles will enter site in forward
     gear, unload materials and exit site in forward gear.

     McNab will advise trucks and construction vehicles of the accepted entry and exit routes to the site.
     Delivery routes will take into consideration of the traffic volumes and requirements of a safe and
     effective flow of traffic within the area.

     Construction vehicles are not to queue in any of the surrounding streets.

2.2 Temporary Vehicular Access

     Vehicle access to site will be via Gympie Terrace. Vehicles will be able to enter and exit site in
     forward gear. Where considered necessary or when demanded under the conditions of any permit,
     accredited & Queensland transport licensed traffic controllers shall be used to direct traffic. All
     traffic will be stopped or diverted in accordance with the methods set out in the Manual of Uniform
     Traffic Control Devices (MUTCD).

2.3 Temporary Closures

     During the course of construction there will be limited instances where McNab will be required to
     partially close a road, footpath and/or car spaces to safely undertake the works. Where any road,
     footpath or car space closures are required, approvals/permits must be obtained from the relevant
     authority/s.


2.4 Loading/Unloading

     Deliveries must be registered each day with the site team during the Pre-Start Meeting. The Site
     Manager will ensure that impact on the local traffic is minimised. Unloading and loading will be
     performed within the noted zones by the use of the crane, materials hoists, and forklift or by hand.

     No unloading or loading will be permitted on the footpath without an approved Traffic Management
     Plan in place and approved by the relevant authority/s. The frequency of deliveries shall be in line
     with the construction programming. In order to limit deliveries, the Contract Administrator will
     ensure a system of Just in Time ordering is implemented.




                                                        05-DOC-001 Rev 0 - Construction Management Plan p6 of 16

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.