qldBUILT Construction Management Plan - JURA Rev02 · MCU23/0094
Plans and drawings: the text below has words only, no drawings.
Very large file (17.3 MB): may take a few minutes to open.
www.invarion.com
W
TRAFFIC GUIDANCE SCHEME (TGS)
N TGS DIAGRAM #
QLDBUILT EUMUNDI NOOSA RD NOOSAVILLE QLDEUMUTGS5
S
RESIDENTIAL DEVELOPMENT TRUCKS REVERSING HOLD & RELEASE
E
STAR
BOAR
D AV
E
TC
DR
IVE
A
S
DAEH
AF
KROW 90m
WO AD
EL
DAOR
RO D
Y
EN
RK
END 15m
DO N
ROAD
WORK
OT O
PREP
DRIVE SAFELY
VERTA
STOP
TO
ARE
REDUCE SPEED
20m
EK
AHEAD
WORK
ROAD
45m
D
SA R
DI NOO
EUMUN
LEGEND
= SHORT TERM SIGNAGE PLACEMENT
= DEVELOPMENT AREA TGS NOTES
THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH THE QGTTM AND AS1742.3
= SPOTTER 2) ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC.
3). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED.
4). SIGNAGE PRESENT FOR UP TO TWO WEEKS MAY BE ERECTED ON PORTABLE LEGS 200mm ABOVE THE SHOULDER SURFACE TO THE BOTTOM EDGE OF THE SIGN.
TC
= TRAFFIC CONTROLLER 5). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.
6). TRAFFIC CONTROLLER AHEAD / PREPARE TO STOP (TCA/PTS) SIGN MUST BE PLACED AT LEAST 90m IN ADVANCE OF CONTROL POINT.
= TRUCK REVERSE PATH 7). TCA / PTS SIGNS SHALL NOT BE DISPLAYED WHEN THE TRAFFIC CONTROLLER IS NOT ACTUALLY IN ATTENDANCE CONTROLLING TRAFFIC.
8). SPOTTER TO ASSIST WITH PEDESTRIAN MANAGEMENT WHILST TRUCKS REVERSE INTO SITE
= DELIVERY VEHICLE 9). FOR ADDITIONAL NOTES & GUIDANCE PLEASE REFER TO THE TGS COVER SHEETS SUPPLIED WITH THIS DIAGRAM.
TGS DETAILS: TGS# QLDEUMUTGS5 CLIENT / TRAFFIC MANAGEMENT DETAILS SITE DETAILS TRAFFIC MANAGEMENT TIME FRAMES DESIGNER DETAILS
REV DATE DESCRIPTION CLIENT NAME: QLDBUILT LOCATION: EUMUNDI NOOSA RD TGS IMPLEMENTATION DATE: TBA
REVISIONS
00 13/02/24 PRODUCED FOR CONSTRUCTION PROJECT MANAGER: DOMINIC TYACKE 0410 332 167 PRIMARY ROAD AFFECTED: EUMUNDI NOOSA RD PROJECT DURATION: UP TO 14 MONTHS Kyle Halliday
Dept. Transport & Main Roads
01 SITE CONTACT: LANCE HOLLAND 0432 028 810 AFFECTED ROAD 2: STARBOARD AVE DURATION OF THIS PHASE: UP TO 1 DAY PERIODIC Traffic Management Design
02 TRAFFIC CONTROL Co: TBA AFFECTED ROAD 3: N/A HOURS OF OPERATION: 09001400 Certification # OP1503
03 NOMINATED TC CONTACT: TBA ORIGINAL POSTED SPEED: 60Km/H TERM OF WORKS SHORT TERM
TGS REVIEWED BY GUY HALLIDAY TMD # OP259 TRAFFIC MANAGEMENT: STATIC WORKSITE REGULATORY WORKSITE SPEED LIMIT: 40Km/H
PRINT TO A3 NOT TO SCALE CONTROL METHOD: HOLD & RELEASE ROAD TYPE: TWO WAY
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.