qldBUILT Construction Management Plan - JURA Rev02 · MCU23/0094
Plans and drawings: the text below has words only, no drawings.
Very large file (17.3 MB): may take a few minutes to open.
Potential Safety Hazards Applicable TGS Risk rating Control Measures Risk rating
before controls after controls
To TRAFFIC L C R# Eliminate / Substitute Engineer / Isolate Administrative L C R#
☐ Road closure
Work area temporarily 5,6,4,8 L1 C2 R1 ☐ Escort / pilot vehicle ☒ Speed reduction L3 C3 R3
☐ Turn lane closure
occupies / obstructs the ☐ Portable traffic signals ☐ Extra signs / VMS
traffic lane, i.e. tree lopping, ☒ Part lane closure ☒ Warning signs
☐ Turn lane Closure with
crane lifts etc ☒ Shoulder closure
delineation ☐ Other
☒ Present ☐ Not Present ☐ Detour ☒ Traffic controller/s / Hold - Release
☐ Temporary road /
lane closure
Travel path unclear through, ☐ Lateral Shift ☐ Clear delineation of travel ☐ Speed reduction
past or around work area ☐ Lane closure path & worksite ☐ Warning / advisory signs
☐ Turn lane closure ☐ Traffic controller/s
☐ Present ☒ Not Present ☐ Additional warning signs
☐ Shoulder closure ☐ Correct cone / bollard ☐ VMS
☐ Detour spacing ☐ Other
☐ Sidetrack
Excavations in work area – ☐ Lateral Shift
☐ Safety barriers ☒ Speed reduction
☐ >500mm ☐ Lane closure
☒ Increase separation from ☒ Warning Signs
☐ Shoulder closure
☐ 251 – 500mm vehicular traffic ☐ Other
☐ 50 – 250mm ☐ Detour ☒ Close delineation
☐ Present ☒ Not Present
☐ Side track ☐ Other
☐ Road closure
Rough or unsealed road ☐ Clear delineation of travel ☐ Speed reduction
☐ Lane closure
surface due to roadworks path & worksite ☐ Warning signs / VMS
☐ Shoulder closure ☐ Escort / pilot vehicle
☐ Present ☒ Not Present ☐ Other
☐ Detour ☐ Other
☐ Side track
Queue lengths might extend ☐ Road closure ☐ Traffic Controller/s in side ☐ Reduce hold time / adjust
across side roads, ☐ Detour roads work method
intersections and / or ☐ Side track ☐ Portable traffic signals ☐ Repeater advance warning signs
through roundabouts
☐ Reduce hold time / ☐ Truck Mounted Attenuator ☐ Calculate End of Queue point
☐ Present ☒ Not Present adjust work method ☐ Other ☐ Other
☐ Road closure
High volume of heavy ☐ Adequate lane widths ☐ Repeater advance warning signs
☐ Heavy vehicle
vehicles past the worksite ☐ Other ☐ Speed reduction
detour
☐ Present ☒ Not Present ☐ Other
☐ Side track
☐ Works at a
different time of
the day
Work during peak traffic All L1 C3 R2 ☒ Works at a different L1 C5 R3
☒ Maintain constant flow of ☒ Keep traffic delays to a minimum
periods time / day
traffic ☒ Warning signs
☐ Detour / alternative
☒ Present ☐ Not Present ☒ Maintain original number ☐ Other
route
of lanes
☐ Other
☐ Portable Traffic signals
☐ Other
Pedestrians diverted to 2,2A,9,9A L2 C2 R2 ☐ Lane closure L3 C3 R3
☒ Traffic controller/s ☒ Speed reduction
areas / crossing points that ☒ Shoulder closure
☐ Safety barriers ☒ Warning signs / VMS
drivers are not expecting. ☐ Hold traffic ☒ Clear delineation of temp.
temporarily path
7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.