EXAMPLES OF CORRECT SIGNAGE MOUNTING
FOR SIGNAGE PLACEMENT, LONG TERM
GENERALLY MEANS LONGER THAN TWO WEEKS.
LONG TERM PLACEMENT ON POSTS
• ON KERBED ROADS IN BUILT UP AREAS ADJACENT TO FOOTPATHS OR
WHERE VEHICLE PARKING MAY OCCUR, THEY SHOULD BE ERECTED A
MINIMUM OF 2.2m MIN FROM LEVEL OF KERB OR FOOTPATH TO
UNDERSIDE OF SIGN.
• SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY DISPLAYED
TO TRAFFIC AND WILL COMMAND ATTENTION.
• SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED PATH
WHERE PRACTICABLE.
LONG TERM PLACEMENT ON POSTS
• WHERE NEITHER PEDESTRIANS OR PARKED VEHICLES HAVE TO BE
CONSIDERED, A MOUNTING HEIGHT OF 1.5m MIN FROM LEVEL OF SHOULDER
SURFACE TO UNDERSIDE OF SIGN MAY BE MORE APPROPRIATE, E.G MEDIANS,
ISLANDS, OPEN ROAD AREAS ETC.
• SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY DISPLAYED TO
TRAFFIC AND WILL COMMAND ATTENTION.
• SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED PATH
WHERE PRACTICABLE.
SHORT TERM PLACEMENT OF SIGNS
• SIGNS MOUNTED ON PORTABLE SUPPORTS (LEGS) SHOULD BE A
MINIMUM HEIGHT OF 200mm FROM THE SHOULDER SURFACE TO THE
BOTTOM EDGE OF THE SIGN.
• SHORT TERM SIGNS SHOULD BE PLACED SO THAT THEY ARE
PROMINENTLY DISPLAYED TO TRAFFIC AND WILL COMMAND ATTENTION.
• IN BUILT UP AREAS, SIGNS SHOULD BE PLACED BEHIND THE KERB IF
VISIBLE TO ONCOMING TRAFFIC. IF SIGNS HAVE TO BE PLACED ON THE
PAVEMENT, THEY SHOULD BE PLACED AS NEAR AS PRACTICABLE TO THE
KERB WITHOUT BECOMING OBSCURED OR OBSTRUCTING MOVING
TRAFFIC.
• SIGNS ARE NOT PERMITTED TO BE PLACED IN OR OBSTRUCT BICYCLE
LANES UNDER ANY CIRCUMSTANCES
• IF SIGNS ARE PLACED ADJACENT TO OR PARTLY ON A FOOTPATH,
A TRAFFIC CONE OR BOLLARD SHOULD BE PLACED AGAINST THE SIGN TO
WARN PEDESTRIANS AND CYCLISTS OF ITS PRESENCE.
• SIGNS MAY NEED TO BE WEIGHTED DOWN WITH SAND BAGS IN WINDY
CONDITIONS OR OVERNIGHT TO ENSURE STABILITY.
Note: In all cases,
1. Traffic Management signage may only be placed in position by a person who holds a Traffic Management
Implementation (TMI) qualification.
2. Implementation of signs should be done in accordance with a Traffic Guidance Scheme designed by a Traffic Management
Design qualified person.
3. Any changes to a Traffic Guidance Scheme may only be authorised by a Traffic Management Design qualified
person.
14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.