qldBUILT Construction Management Plan - JURA Rev02 · MCU23/0094

of 81

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (17.3 MB): may take a few minutes to open.

Log in to see the plans as drawn
 FPE Ref: 6693-240215-1.0



          6.1      SOIL & WATER QUALITY MANAGEMENT

          Incidents           ▪   Mobilisation of sediment from the site into the down gradient drainage system.

                              ▪   Undertake a survey of erosion and sediment control measures and determine effectiveness of current controls.
          Corrective
                              ▪   Reassess the risks of the works areas and determine if further controls will remedy any problems.
          Actions
                              ▪   Seek the assistance of an appropriately qualified professional for advice on erosion sediment control devices.


          6.2      GROUNDWATER MANAGEMENT STRATEGY

          Objective           To manage the environmental impacts on groundwater associated with staged works, such as excavation of foundations and infrastructure




                                                                                               T
                              proposed. No Groundwater was encountered during geotechnical investigations applicable to the construction phase, however there remains a risk




                                                                                      AF
                              of groundwater interactions.




                                                                                R
          Potential impacts   Discharged groundwater to surface drains; groundwater degradation or groundwater drawdown – lowering of the water table.



                                                                          D
                              ▪   No discharged groundwater to surface drains
          Performance
                              ▪   No permanent groundwater degradation
          Criteria
                              ▪   No groundwater drawdown
                              ▪   No accidental or uncontrolled release of waters from site
                              ▪   Prior to commencement of works assess groundwater conditions to determine construction management procedures
          Control Measures
                              ▪   Establish management strategies for situations where groundwater inflow is excessive and where pumping may be required (i.e. cut-off drain)
                              ▪   Similarly follow Soil and Water Management Procedures as set out in section 6.1 to manage impacts and prevent degradation of groundwater.
                              ▪   Appropriately integrate the development into the site.




15 February 2024                                            Construction Environmental Management Plan                                                                          11
                                                  79 - 83 Eumundi Noosa Road & 26 Headland Drive, Noosaville QLD

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.