 FPE Ref: 6693-240215-1.0



          6.2      GROUNDWATER MANAGEMENT STRATEGY
                            ▪   Develop effective and flexible control plans based on anticipated groundwater, weather and construction conditions.
                            ▪   Minimise the extent and duration of ground disturbance.
                            ▪   Control water movement through the site – establish a bypass for ‘clean’ water to minimise interaction with areas of soil disturbance.
                            ▪   Minimise soil erosion.
                            ▪   Promptly stabilise disturbed areas – progressive stabilisation as quickly as possible is desirable, particularly in high erosion risk areas (i.e.,
                                batters and drains).
                            ▪   Maximise sediment retention on the site.




                                                                                               T
                            ▪   Always maintain all erosion and sediment control measures in proper working order.




                                                                                     AF
                            ▪   Monitor the site and adjust erosion and sediment control practices to maintain the required performance standard. If heavy rain / storms forecast
                                stabilise/protect exposed areas and reinforce erosion and sediment controls to minimise hydraulic damage. Cease earthworks during rainfall




                                                                               R
                                events likely to generate runoff.
                            ▪   Stockpiles of soil not used within 24 hrs should be covered or ringed by sediment fences/bunds. Stockpiles shall be located outside of overland


                            ▪
                                flow paths.
                                                                         D
                                Maintain a register of ground water quality logs, including a record of the time and nature all incidents to be kept for verification of compliance
                                on an as-needs basis.
                            ▪   Control devices will be checked daily and after rainfall events, and re-established/ maintained as required.
          Monitoring
                            Weekly inspections will be carried out to check:
                            ▪   Works are only occurring within designated area; and
                            ▪   Control measures to ensure they are maintained in working order.




15 February 2024                                           Construction Environmental Management Plan                                                                                 12
                                                 79 - 83 Eumundi Noosa Road & 26 Headland Drive, Noosaville QLD

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.