6.6 AIR QUALITY & NOISE MANAGEMENT
▪ Quantitative dust monitoring is complaint driven unless requested by the administering authority.
Reporting ▪ Construction Foreman to maintain a log of relevant daily meteorological conditions, inspections and maintenance actions completed (including
improvements).
▪ The log is to be kept for verification of compliance on an as needs basis.
▪ Maintain a register of air quality and noise related complaints, including a record of the time and nature of the alleged incident to aid in
complaint verification.
T
Incidents ▪ Dust plumes visible outside the site boundary.
AF
▪ Complaints of noise or dust received from neighbouring properties.
Corrective ▪ All complaints will be addressed by following the complaints procedure (Section1.9).
R
Actions ▪ Reinforce requirements and triggers for dust control.
D
▪ Limit periods of excessive noise as far as possible.
15 February 2024 Construction Environmental Management Plan 21
79 - 83 Eumundi Noosa Road & 26 Headland Drive, Noosaville QLD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.