Council archive · source document
Attachment 2A - Emergency Management Plan Noosa - Final · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
FM – 6.3.5 Emergency Management Plan template
Flooding – Potential Impacts
The greatest threats to the resort are a failure of one or both of the following systems:
1. The Central Facilities Stormwater pumps system. This system discharges water runoff
from the underground Precinct car parks and the C/F underground car park. A
mechanical / electrical failure to this system will cause the inundation of the mentioned
areas.
2. The Sewage pumps station. SEE BCP for event action
Flooding Preparedness
The Flooding emergency response plan is structured around 4 important stages:
STAGE 1: Continual heavy rainfall
STAGE 2: Flooding standby (12 – 24 hours prior to potential flooding)
STAGE 3: Flood alert warning (6 hours prior to imminent flooding)
STAGE 4: Post emergency condition / clean up.
At each of these stages are critical tasks that are to be performed by key emergency personnel,
for example the checking of stormwater pumps and equipment, stockpiling material and
supplies, sandbagging critical areas and infrastructure, and shutting off sewerage valves.
During these high-risk periods the Maintenance Department will continually monitor the radar
and weather condition reports that are being issued by the Bureau of Meteorology
(www.bom.gov.au).
Flood Emergency Equipment
The resort has several stormwater pumps and drainage systems located within the site to assist
with the drainage of storm water resulting from heavy rainfall. It is important that these pumps
and drainage systems are monitored to ensure they do not become blocked or fail to operate.
The resort currently holds the following backup emergency equipment to be utilised for flood
emergencies:
• Supply of sandbags (additional bags purchased when required)
• Backup pump and associated equipment
• Plastic sheeting
• Wet weather attire
Document Title: Issue: 6 Next review date:
FM – 6.3.5 Emergency Management Plan Review date: February 2026 June 2026
Noosa Resort
Document Owner: Authorised by: Page: 53 of 77
Health Safety & Wellbeing Manager HSW
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2A - Emergency Management Plan Noosa - Final.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.