4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines
and the approved Plan of Development. The approved plan is titled and numbered Landscape
for Operational Works Approval, Job Number LGRR 1168, Drawing Number LA 01, Sheet 1 of
1, Issue A, prepared by Land Graphics dated December 2006 and may be amended by these
conditions.
2. All manholes, inspection pits and grates are to be raised to finished surface levels and kept
free of cover and be visible at all times to ensure prompt access in case of emergency.
3. The landscape construction is to be implemented in accordance with the amended landscape
plan, planting schedule and horticultural industry best practices.
4. All trees must be planted a minimum of 1 metre from all services.
5. This Development Permit lapses if the development has not happened by 7 March 2009,
unless application to extend the currency is approved by Council.
Land Development
6. The development shall be carried out in accordance with Engineering Drawings Nos:-
06668-C1A dated 15 December 2006 by Tod Noosa
06668-C2A dated 15 December 2006 by Tod Noosa
06668-C3A dated 15 December 2006 by Tod Noosa
06668-C4A dated 15 December 2006 by Tod Noosa
06668-C5A dated 15 December 2006 by Tod Noosa
07138-H-401 dated 4 September 2008 by Burnett Lynch MRP
07138-H-402 dated 4 September 2008 by Burnett Lynch MRP
07138-H-403 dated 4 September 2008 by Burnett Lynch MRP
06668-S20J dated August 2009 by Tod Noosa
or as modified herein.
7. Roof and surface runoff connection to internal infiltration drainage system shall be as shown
on drawing Nos. 07138-H-401,07138-H-402 & 07138-H-403 (Burnett Lynch MRP).
8. Prior to the commencement of works a Traffic Management Plan shall be submitted to Council
prior to the pre start meeting. The Traffic Management Plan shall address:-
8.1. The movement of trucks to and from the site, in particular when removing excavated
material from the site.
8.2. The provision of signage and traffic controllers, so as delays to general traffic using the
streets in the vicinity of the development are avoided.
9. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval - 010.2006.00000174.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 57 KB (small file)
- File type
No other editions are linked here.