2003/221132
117. Prior to excavating any material to be used for fill on this site, a Development Permit for
Operational Works shall have been obtained for the site from which the excavated material is
taken. A soil report shall be submitted with the application certifying that the material is free of
acid sulphate soils and other deleterious materials.
118. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particulate matter escapes onto a public road. All vehicles carrying materials either to
or from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
119. A program of works is to be submitted at the Prestart meeting detailing the construction
schedule and proposed environmental protection measures.
Where the program is changed for any reason whatsoever, a copy of the revised program
shall be submitted to Council’s Works Inspector within seven (7) days.
120. For the following classes of work associated with development, a Development Permit for
Operational Works must be obtained prior to commencement of works relating to that class of
work. The application may combine any or all of these classes of work:
120.1.Site Civil Works;
120.2.Roadworks;
120.3.Stormwater Drainage;
120.4.Frontage works;
120.5.Sewer reticulation including new mains, relocations, diversions, pump stations and
rising mains;
120.6.Water reticulation;
120.7.Site Filling;
120.8.Excavation of materials to fill another site; and
120.9.Landscaping.
121. Operational works shall be carried out in a manner that prevents:
121.1.Pollution of a waterway;
121.2.Dust/sand nuisance to residents in the vicinity;
121.3.Transfer of dirt and debris onto a public road;
121.4.Excessive noise (less than 1.5 Dba above ambient measured at the lot boundaries);
121.5.Excessive traffic delays (less than 5 minute delays); and
121.6.Diminution of neighbourhood amenity (long term parking of employees vehicles, parking
of construction equipment etc.).
122. A traffic management plan shall be submitted in conjunction with a Development Permit for
Operational Works involving road or drainage works. The plan shall address all phases of
construction to be undertaken on site.
123. Where operational works are likely to affect nearby residents and the Noosa Primary School,
at least 3 days notice of commencement of work, the name of the site supervisor, and a 24
hour contact telephone number shall be distributed to affected residents.
124. Earthworks shall be generally contained within existing and proposed road reserves. Where
earthworks are required for the provision of services, existing contours shall be restored.
125. Fill imported to the site may only be from a site licensed with The Environmental Protection
Agency or from a site for which a Development Permit for Operational Works has been issued
approving the export of fill.
Page 20 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Change to an Existing Approval (Construction Staging Plan) [As Published]Related documentApplication case desk ↗
About this file
- File size
- 123 KB (small file)
- File type
No other editions are linked here.