3.5 POST-DEVELOPMENT SITE XP-STORM
3.5.1 CATCHMENT DATA
Table 6 presents the post-development catchment details. Drawing No. M3024E_DA1_SK02 in
Appendix D presents the catchment delineation.
Table 6 – Post-Development Catchment Data
Fraction Vectored Slope
Catchment Area (ha)
Impervious (%)
D1 0.0335 100% 10%
D2 0.0121 66% 10%
D3 0.0030 100% 10%
Total 0.0486 92% 10%
The following catchment arrangements have been modelled:
5% AEP from catchment D1 has been modelled to enter the detention tank. Larger flows bypass
detention.
1% AEP from catchment D2 has been modelled to enter the detention tank.
Catchment D3 bypasses the detention tank.
Figure 5 presents the XP-STORM layout for the post-development site.
Figure 5 – Post-Development XP-STORM Layout
3.5.2 RAINFALL DATA, HYDROLOGICAL LOSSES & BX FACTOR
As per the pre-development scenario.
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e |8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.